Mechanical Installer
Installation, commissioning and maintenance of mechanical equipment
Mechanical Installer: providing digital handover information for installed equipment
The scenario
A self-employed plumber running a small business has been appointed as a subcontractor to install heating equipment, including boilers, pumps and valves, on the extension and refurbishment of a post-primary school: a €14 million public project for an Education and Training Board. The plumber is experienced in installing and commissioning mechanical systems but new to formal digital information management. The main contractor requires installation records, product information, commissioning results, warranties and maintenance documentation in an agreed format through the project's . The plumber needs a simple, low-cost workflow to deliver complete handover information for every installed item, without extra software or specialist staff, ready for authorization by the main contractor and acceptance by the client by July 2027.
Handover information for every installed item is complete, in the agreed format and submitted through the project's CDE, without extra software or specialist staff.
How you will know
- The information required for each item of equipment is known before installation starts.
- Installation details and photographs are captured on site with a phone or tablet.
- Product, commissioning, warranty and maintenance records are organised in the agreed format.
- Compliance records and certificates are provided with the handover information.
- Information is submitted through the project's CDE without repeated requests for missing items.
By 01/07/2027.
A Mechanical Installer, when the main contractor requires installation, commissioning and maintenance information to be submitted digitally through the project's CDE, must provide the digital handover information for installed heating equipment.
Activity flow diagram
Choose Vertical to follow the flow from top to bottom on a narrow screen.
Scroll sideways to follow the flow. With the diagram focused, use the Left and Right arrow keys.
- Mechanical Installer
- Lead appointed party (main contractor)
- Issue
- Submit
- Review
- Accept
- Reject
- Returns work to amend and resubmit
Explore the flow by stage
6 stages · 1 decision with 3 optionsChoose a stage to see what each party does in it, the hand-offs between them and any decision that follows. A decision's options are listed under it. The hand-off numbers match the numbered arrows on the diagram.
Each stage below shows what each party does in it, the hand-offs between them and any decision that follows. A decision's options are listed under it. The hand-off numbers match the numbered arrows on the diagram. Each stage's checklist is in the Full Scenario Record.
Decision after stage 2How will installation records be captured on site?One option applies.
Stage 1: Clarify heating equipment handover information requirements
Mechanical Installer
Review the main contractor's information requirements for the school extension and refurbishment to find out exactly which attributes, serial numbers and certificates are needed for each item of heating equipment before installation starts.
Responsible: Mechanical Installer
Who does what at this stage
Mechanical Installer
The role
Carries out stage 1
Clarify heating equipment handover information requirements
- Receives 1: Asset data fields and handover requirements from Lead appointed party (main contractor) (issue)
Lead appointed party (main contractor)
ISO 19650 party
- Sends 1: Asset data fields and handover requirements to Mechanical Installer (issue)
Hand-offs at this stage
1Asset data fields and handover requirements
- From
- Lead appointed party (main contractor)
- To
- Mechanical Installer
- Hand-off
- Issue
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 1 | Lead appointed party (main contractor) | Mechanical Installer | Issue | Asset data fields and handover requirements |
Checklist
0 of 8 ticked- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates - Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations - Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Equipment commissioning report · Information Use · Verified
- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates - Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations - Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Equipment commissioning report · Information Use · Verified
- Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information naming conventions and metadata standards
- Project information naming conventions and metadata standards · Information Use · Verified
- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates - Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations
- Equipment commissioning report · Information Use · Verified
- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates - Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations - Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Equipment commissioning report · Information Use · Verified
- Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing
- Exchange Information Requirements (EIR) · Information Use · Verified
- Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing
- Exchange Information Requirements (EIR) · Information Use · Verified
- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates - Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations - Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Equipment commissioning report · Information Use · Verified
Stage 2: Agree CDE upload protocols and naming conventions
Mechanical Installer
Establish standard data capture sheets and project information naming conventions and metadata standards with the main contractor to enable straightforward CDE submissions without specialist software.
Responsible: Mechanical Installer
Who does what at this stage
Mechanical Installer
The role
Carries out stage 2
Agree CDE upload protocols and naming conventions
Then decides: How will installation records be captured on site?
- Receives 2: CDE upload protocols and naming conventions from Lead appointed party (main contractor) (issue)
Lead appointed party (main contractor)
ISO 19650 party
- Sends 2: CDE upload protocols and naming conventions to Mechanical Installer (issue)
Hand-offs at this stage
2CDE upload protocols and naming conventions
- From
- Lead appointed party (main contractor)
- To
- Mechanical Installer
- Hand-off
- Issue
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 2 | Lead appointed party (main contractor) | Mechanical Installer | Issue | CDE upload protocols and naming conventions |
Decision: How will installation records be captured on site?
After stage 2: Agree CDE upload protocols and naming conventions. One option applies. Marks show how well each option meets a criterion. They are not scores, and they are not added up or ranked.
| Criterion | Option 2.1A phone or tablet app | Option 2.2Paper sheets, then digitised | Option 2.3The main contractor's CDE app |
|---|---|---|---|
| Hardware and software availabilityDoes the capture method match available IT resources without requiring specialist software? Evidence: E1 Raise needed changes to the project's information production methods and procedures with the main contractor; E5 Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project
| +Strong Uses standard mobile hardware already available to site personnel without specialist desktop software. Evidence: E1 Raise needed changes to the project's information production methods and procedures with the main contractor
| +Strong Requires zero digital hardware on site, relying on standard paper proformas. Evidence: E1 Raise needed changes to the project's information production methods and procedures with the main contractor
| ~Depends Relies entirely on the main contractor deploying, licensing, and configuring an accessible CDE mobile app. Evidence: E5 Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project; E1 Raise needed changes to the project's information production methods and procedures with the main contractor
|
| Metadata and naming complianceHow reliably does the method enforce ISO 19650 naming conventions, status codes, and revision metadata? Evidence: E2 Apply the project's agreed naming conventions and metadata to digital deliverables; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization; E6 Project information naming conventions and metadata standards
| ~Depends Requires manual or preconfigured discipline to ensure field tags align with agreed metadata standards. Evidence: E2 Apply the project's agreed naming conventions and metadata to digital deliverables; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
| –Weak Manual paper records risk transcription errors when later assigning file naming and metadata codes. Evidence: E2 Apply the project's agreed naming conventions and metadata to digital deliverables; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
| +Strong The contractor app directly embeds project-wide naming conventions, status codes, and revision schemas. Evidence: E2 Apply the project's agreed naming conventions and metadata to digital deliverables; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization; E6 Project information naming conventions and metadata standards
|
| Directness of CDE workflowHow smoothly does the captured record transition into the common data environment workflow states? Evidence: E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
| ~Depends Captured records still need subsequent export and upload into the project common data environment. Evidence: E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
| –Weak Introduces a weekly digitisation bottleneck before information can enter the CDE shared workflow. Evidence: E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
| +Strong Information enters the CDE work-in-progress state directly at the point of site capture. Evidence: E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
|
Option 2.1
A phone or tablet app
- Option 2.1: Capture records with a phone or tablet app
Rejoins at stage 3: Capture on-site equipment details and photographs.
- Hardware and software availability
- +StrongUses standard mobile hardware already available to site personnel without specialist desktop software.
Evidence: E1 Raise needed changes to the project's information production methods and procedures with the main contractor
Raise needed changes to the project's information production methods and procedures with the main contractor · Action Statement · Verified
identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement.Instruction
See the full evidence entry
- Metadata and naming compliance
- ~DependsRequires manual or preconfigured discipline to ensure field tags align with agreed metadata standards.
Evidence: E2 Apply the project's agreed naming conventions and metadata to digital deliverables; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
Apply the project's agreed naming conventions and metadata to digital deliverables · Action Statement · Suggested – review
See the full evidence entryUpload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entry
- Directness of CDE workflow
- ~DependsCaptured records still need subsequent export and upload into the project common data environment.
Evidence: E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
Upload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entry
Consequences
- Data and photos are captured digitally on site and formatted for CDE upload protocol requirements.
Evidence: E4 Equipment commissioning report; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the full evidence entryUpload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entry
- Site operatives capture digital photos and asset data immediately on handheld devices without bulky paper handling.
Evidence: E1 Raise needed changes to the project's information production methods and procedures with the main contractor
Raise needed changes to the project's information production methods and procedures with the main contractor · Action Statement · Verified
identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement.Instruction
See the full evidence entry
- Data must be batched and uploaded to the project CDE following agreed naming conventions.
Evidence: E2 Apply the project's agreed naming conventions and metadata to digital deliverables; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
Apply the project's agreed naming conventions and metadata to digital deliverables · Action Statement · Suggested – review
See the full evidence entryUpload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entry
Evidence: E1 Raise needed changes to the project's information production methods and procedures with the main contractor; E2 Apply the project's agreed naming conventions and metadata to digital deliverables; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization; E4 Equipment commissioning report
Raise needed changes to the project's information production methods and procedures with the main contractor · Action Statement · Verified
identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement.Instruction
See the full evidence entryApply the project's agreed naming conventions and metadata to digital deliverables · Action Statement · Suggested – review
See the full evidence entryUpload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entryEquipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the full evidence entry
Option 2.2
Paper sheets, then digitised
- Option 2.2: Record on paper and digitise each week
Rejoins at stage 3: Capture on-site equipment details and photographs.
- Hardware and software availability
- +StrongRequires zero digital hardware on site, relying on standard paper proformas.
Evidence: E1 Raise needed changes to the project's information production methods and procedures with the main contractor
Raise needed changes to the project's information production methods and procedures with the main contractor · Action Statement · Verified
identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement.Instruction
See the full evidence entry
- Metadata and naming compliance
- –WeakManual paper records risk transcription errors when later assigning file naming and metadata codes.
Evidence: E2 Apply the project's agreed naming conventions and metadata to digital deliverables; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
Apply the project's agreed naming conventions and metadata to digital deliverables · Action Statement · Suggested – review
See the full evidence entryUpload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entry
- Directness of CDE workflow
- –WeakIntroduces a weekly digitisation bottleneck before information can enter the CDE shared workflow.
Evidence: E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
Upload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entry
Consequences
- Site teams record data manually on paper sheets and must scan or transcribe records weekly.
- Site teams avoid hardware issues in harsh environments but incur weekly manual digitisation effort.
Evidence: E1 Raise needed changes to the project's information production methods and procedures with the main contractor
Raise needed changes to the project's information production methods and procedures with the main contractor · Action Statement · Verified
identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement.Instruction
See the full evidence entry
- Risk of missing or misapplied status and revision metadata increases during delayed back-office uploads.
Evidence: E2 Apply the project's agreed naming conventions and metadata to digital deliverables; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
Apply the project's agreed naming conventions and metadata to digital deliverables · Action Statement · Suggested – review
See the full evidence entryUpload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entry
Evidence: E1 Raise needed changes to the project's information production methods and procedures with the main contractor; E2 Apply the project's agreed naming conventions and metadata to digital deliverables; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
Raise needed changes to the project's information production methods and procedures with the main contractor · Action Statement · Verified
identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement.Instruction
See the full evidence entryApply the project's agreed naming conventions and metadata to digital deliverables · Action Statement · Suggested – review
See the full evidence entryUpload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entry
Option 2.3
The main contractor's CDE app
- Option 2.3: Enter records directly in the contractor's CDE app
Rejoins at stage 3: Capture on-site equipment details and photographs.
- Hardware and software availability
- ~DependsRelies entirely on the main contractor deploying, licensing, and configuring an accessible CDE mobile app.
Evidence: E5 Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project; E1 Raise needed changes to the project's information production methods and procedures with the main contractor
Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project · Action Statement · Verified
| Amendments (BIM execution plan) | identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement. | detail changes that need to be made to the project’s information production methods and procedures and the project’s information standard | | IT Resources (BIM execution plan) | identify Information Technologies Resources available for use on the project | detail the lead appoInstruction
See the full evidence entryRaise needed changes to the project's information production methods and procedures with the main contractor · Action Statement · Verified
identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement.Instruction
See the full evidence entry
- Metadata and naming compliance
- +StrongThe contractor app directly embeds project-wide naming conventions, status codes, and revision schemas.
Evidence: E2 Apply the project's agreed naming conventions and metadata to digital deliverables; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization; E6 Project information naming conventions and metadata standards
Apply the project's agreed naming conventions and metadata to digital deliverables · Action Statement · Suggested – review
See the full evidence entryUpload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entryProject information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the full evidence entry
- Directness of CDE workflow
- +StrongInformation enters the CDE work-in-progress state directly at the point of site capture.
Evidence: E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
Upload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entry
Consequences
- Installers populate the main contractor's CDE app directly with photo records and status metadata.
Evidence: E4 Equipment commissioning report; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the full evidence entryUpload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entry
- Data enters the project common data environment seamlessly without secondary manual upload steps.
Evidence: E3 Upload checked handover information containers to the common data environment for the main contractor's authorization
Upload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entry
- Site personnel must be trained on the contractor's specific mobile interface and permissions.
Evidence: E5 Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project
Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project · Action Statement · Verified
| Amendments (BIM execution plan) | identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement. | detail changes that need to be made to the project’s information production methods and procedures and the project’s information standard | | IT Resources (BIM execution plan) | identify Information Technologies Resources available for use on the project | detail the lead appoInstruction
See the full evidence entry
Evidence: E5 Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project; E1 Raise needed changes to the project's information production methods and procedures with the main contractor; E2 Apply the project's agreed naming conventions and metadata to digital deliverables; E3 Upload checked handover information containers to the common data environment for the main contractor's authorization; E6 Project information naming conventions and metadata standards; E4 Equipment commissioning report
Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project · Action Statement · Verified
| Amendments (BIM execution plan) | identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement. | detail changes that need to be made to the project’s information production methods and procedures and the project’s information standard | | IT Resources (BIM execution plan) | identify Information Technologies Resources available for use on the project | detail the lead appoInstruction
See the full evidence entryRaise needed changes to the project's information production methods and procedures with the main contractor · Action Statement · Verified
identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement.Instruction
See the full evidence entryApply the project's agreed naming conventions and metadata to digital deliverables · Action Statement · Suggested – review
See the full evidence entryUpload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entryProject information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the full evidence entryEquipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the full evidence entry
Checklist
0 of 8 ticked- Apply the project's agreed naming conventions and metadata to digital deliverables · Action Statement · Suggested – reviewSee the evidence: Apply the project's agreed naming conventions and metadata to digital deliverables
- Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information naming conventions and metadata standards - Upload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – reviewSee the evidence: Upload checked handover information containers to the common data environment for the main contractor's authorization
- Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Upload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – reviewSee the evidence: Upload checked handover information containers to the common data environment for the main contractor's authorization
- Exchange Information Requirements (EIR) · Information Use · Verified
- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report
- Equipment commissioning report · Information Use · Verified
- Upload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – reviewSee the evidence: Upload checked handover information containers to the common data environment for the main contractor's authorization
- Apply the project's agreed naming conventions and metadata to digital deliverables · Action Statement · Suggested – reviewSee the evidence: Apply the project's agreed naming conventions and metadata to digital deliverables
- Upload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – reviewSee the evidence: Upload checked handover information containers to the common data environment for the main contractor's authorization
- Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information naming conventions and metadata standards
- Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project · Action Statement · Verified
| Amendments (BIM execution plan) | identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement. | detail changes that need to be made to the project’s information production methods and procedures and the project’s information standard | | IT Resources (BIM execution plan) | identify Information Technologies Resources available for use on the project | detail the lead appoInstruction
See the evidence: Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project - Raise needed changes to the project's information production methods and procedures with the main contractor · Action Statement · Verified
identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement.Instruction
See the evidence: Raise needed changes to the project's information production methods and procedures with the main contractor
- Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project · Action Statement · Verified
- Raise needed changes to the project's information production methods and procedures with the main contractor · Action Statement · Verified
identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement.Instruction
See the evidence: Raise needed changes to the project's information production methods and procedures with the main contractor
- Raise needed changes to the project's information production methods and procedures with the main contractor · Action Statement · Verified
- Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR)
- Exchange Information Requirements (EIR) · Information Use · Verified
Option 2.1: Capture records with a phone or tablet app
Mechanical Installer · an option of the decision after stage 2: Agree CDE upload protocols and naming conventions
Record each item's details and photographs on a phone or tablet as it is installed, using a low-cost app that exports in the agreed format.
Responsible: Mechanical Installer
Who does what at this stage
Mechanical Installer
The role
Carries out option 2.1
Capture records with a phone or tablet app
Lead appointed party (main contractor)
ISO 19650 party
No part in this stage.
No part in this stage: Lead appointed party (main contractor).
Hand-offs at this stage
No hand-offs at this stage.
Checklist
0 of 4 ticked- Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report
- Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
- Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report
- Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
- Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report
- Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
- Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information naming conventions and metadata standards
- Project information naming conventions and metadata standards · Information Use · Verified
Option 2.2: Record on paper and digitise each week
Mechanical Installer · an option of the decision after stage 2: Agree CDE upload protocols and naming conventions
Keep the familiar paper sheets on site and transfer them into the agreed digital format each week, with photographs filed by equipment reference.
Responsible: Mechanical Installer
Who does what at this stage
Mechanical Installer
The role
Carries out option 2.2
Record on paper and digitise each week
Lead appointed party (main contractor)
ISO 19650 party
No part in this stage.
No part in this stage: Lead appointed party (main contractor).
Hand-offs at this stage
No hand-offs at this stage.
Checklist
0 of 4 ticked- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information naming conventions and metadata standards - Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR)
- Equipment commissioning report · Information Use · Verified
- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report
- Equipment commissioning report · Information Use · Verified
- Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information naming conventions and metadata standards
- Project information naming conventions and metadata standards · Information Use · Verified
- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report
- Equipment commissioning report · Information Use · Verified
Option 2.3: Enter records directly in the contractor's CDE app
Mechanical Installer · an option of the decision after stage 2: Agree CDE upload protocols and naming conventions
Use the main contractor's CDE app on site, if it provides one, so records go straight into the project information system.
Responsible: Mechanical Installer
Who does what at this stage
Mechanical Installer
The role
Carries out option 2.3
Enter records directly in the contractor's CDE app
Lead appointed party (main contractor)
ISO 19650 party
No part in this stage.
No part in this stage: Lead appointed party (main contractor).
Hand-offs at this stage
No hand-offs at this stage.
Checklist
0 of 5 ticked- Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project · Action Statement · Verified
| Amendments (BIM execution plan) | identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement. | detail changes that need to be made to the project’s information production methods and procedures and the project’s information standard | | IT Resources (BIM execution plan) | identify Information Technologies Resources available for use on the project | detail the lead appoInstruction
See the evidence: Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project
- Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project · Action Statement · Verified
- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report
- Equipment commissioning report · Information Use · Verified
- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report
- Equipment commissioning report · Information Use · Verified
- Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information naming conventions and metadata standards
- Project information naming conventions and metadata standards · Information Use · Verified
- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report
- Equipment commissioning report · Information Use · Verified
Stage 3: Capture on-site equipment details and photographs
Mechanical Installer
Record equipment serial numbers, precise locations, and installation dates on a mobile device while fitting heating plant, photographing installed equipment and identification plates.
Responsible: Mechanical Installer
Who does what at this stage
Mechanical Installer
The role
Carries out stage 3
Capture on-site equipment details and photographs
- Sends 3: Equipment details and photographs to Lead appointed party (main contractor) (submit)
Lead appointed party (main contractor)
ISO 19650 party
- Receives 3: Equipment details and photographs from Mechanical Installer (submit)
Hand-offs at this stage
3Equipment details and photographs
- From
- Mechanical Installer
- To
- Lead appointed party (main contractor)
- Hand-off
- Submit
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 3 | Mechanical Installer | Lead appointed party (main contractor) | Submit | Equipment details and photographs |
Checklist
0 of 8 ticked- Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report
- Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
- Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report
- Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
- Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR)
- Exchange Information Requirements (EIR) · Information Use · Verified
- Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information naming conventions and metadata standards
- Project information naming conventions and metadata standards · Information Use · Verified
- Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates - Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations
- Provide the digital handover information for installed heating equipment · Action Statement · Verified
- Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates
- Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
- Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates - Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations - Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Provide the digital handover information for installed heating equipment · Action Statement · Verified
- Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing
- Exchange Information Requirements (EIR) · Information Use · Verified
Stage 4: Collate commissioning, compliance and warranty records
Mechanical Installer
Assemble manufacturer manuals, pressure test results, commissioning records, Building Control (BCAR) ancillary certificates for the mechanical installation, and warranty certificates into structured digital packages for every installed heating item.
Responsible: Mechanical Installer
Who does what at this stage
Mechanical Installer
The role
Carries out stage 4
Collate commissioning, compliance and warranty records
- Sends 4: Commissioning, compliance and warranty records to Lead appointed party (main contractor) (submit)
Lead appointed party (main contractor)
ISO 19650 party
- Receives 4: Commissioning, compliance and warranty records from Mechanical Installer (submit)
Hand-offs at this stage
4Commissioning, compliance and warranty records
- From
- Mechanical Installer
- To
- Lead appointed party (main contractor)
- Hand-off
- Submit
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 4 | Mechanical Installer | Lead appointed party (main contractor) | Submit | Commissioning, compliance and warranty records |
Checklist
0 of 8 ticked- Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations
- Complete commissioning reports using agreed project templates · Action Statement · Verified
- Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations
- Complete commissioning reports using agreed project templates · Action Statement · Verified
- Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations - Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Complete commissioning reports using agreed project templates · Action Statement · Verified
- Collate manufacturer operation and maintenance manuals with warranty certificates · Action Statement · Verified
- EU Directives for: Machinery Safety; Low Voltage; Pressure Equipment; Electromagnetic Compatibility. - Sustainable Energy Authority of Ireland: DEAP 4.2.1 Manual Guide. - Sustainable Energy Authority of Ireland: A Homeowner’s Guide to Heat Pump Systems. - DEFRA/Carbon Trust Energy Technology List – Heat Pumps (www.eca.gov.uk). - I.S. EN 14511:2018 Air conditioners, liquid chilling packages and heat pumps with electrically driven compressors for space heating and cooling. - ISO 13256:1998 WaterSupplementary information – further guidance on heat pumps
See the evidence: Collate manufacturer operation and maintenance manuals with warranty certificates - Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing
- Collate manufacturer operation and maintenance manuals with warranty certificates · Action Statement · Verified
- Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information naming conventions and metadata standards
- Project information naming conventions and metadata standards · Information Use · Verified
- Apply the project's agreed naming conventions and metadata to digital deliverables · Action Statement · Suggested – reviewSee the evidence: Apply the project's agreed naming conventions and metadata to digital deliverables
- Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information naming conventions and metadata standards
- Collate manufacturer operation and maintenance manuals with warranty certificates · Action Statement · Verified
- EU Directives for: Machinery Safety; Low Voltage; Pressure Equipment; Electromagnetic Compatibility. - Sustainable Energy Authority of Ireland: DEAP 4.2.1 Manual Guide. - Sustainable Energy Authority of Ireland: A Homeowner’s Guide to Heat Pump Systems. - DEFRA/Carbon Trust Energy Technology List – Heat Pumps (www.eca.gov.uk). - I.S. EN 14511:2018 Air conditioners, liquid chilling packages and heat pumps with electrically driven compressors for space heating and cooling. - ISO 13256:1998 WaterSupplementary information – further guidance on heat pumps
See the evidence: Collate manufacturer operation and maintenance manuals with warranty certificates - Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing
- Collate manufacturer operation and maintenance manuals with warranty certificates · Action Statement · Verified
- Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing
- Exchange Information Requirements (EIR) · Information Use · Verified
Stage 5: Validate digital handover submissions against acceptance criteria
Mechanical Installer
Validate digital handover submissions against client acceptance criteria and agreed file naming conventions to ensure all required maintenance and compliance documentation is complete.
Responsible: Mechanical Installer
Who does what at this stage
Mechanical Installer
The role
Carries out stage 5
Validate digital handover submissions against acceptance criteria
- Receives 5: Check results and list of missing items from Lead appointed party (main contractor) (review)
Lead appointed party (main contractor)
ISO 19650 party
- Sends 5: Check results and list of missing items to Mechanical Installer (review)
Hand-offs at this stage
5Check results and list of missing items
- From
- Lead appointed party (main contractor)
- To
- Mechanical Installer
- Hand-off
- Review
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 5 | Lead appointed party (main contractor) | Mechanical Installer | Review | Check results and list of missing items |
Checklist
0 of 8 ticked- Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
- Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing - Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing - Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information naming conventions and metadata standards
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
- Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates
- Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information naming conventions and metadata standards
- Project information naming conventions and metadata standards · Information Use · Verified
- Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing - Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR)
Stage 6: Submit completed mechanical records through project CDE
Mechanical Installer
Upload the final verified asset packages to the project CDE, meeting the subcontract handover requirements for the school without repeated requests for missing information.
Responsible: Mechanical Installer
Who does what at this stage
Mechanical Installer
The role
Carries out stage 6
Submit completed mechanical records through project CDE
- Sends 6: Final handover packages through the CDE to Lead appointed party (main contractor) (submit)
- Receives 7: Missing items: amend and resubmit from Lead appointed party (main contractor) (reject)
- Receives 8: Handover information accepted from Lead appointed party (main contractor) (accept)
Lead appointed party (main contractor)
ISO 19650 party
- Sends 7: Missing items: amend and resubmit to Mechanical Installer (reject)
- Sends 8: Handover information accepted to Mechanical Installer (accept)
- Receives 6: Final handover packages through the CDE from Mechanical Installer (submit)
Hand-offs at this stage
6Final handover packages through the CDE
- From
- Mechanical Installer
- To
- Lead appointed party (main contractor)
- Hand-off
- Submit
7Missing items: amend and resubmit
- From
- Lead appointed party (main contractor)
- To
- Mechanical Installer
- Hand-off
- Reject, returns to stage 4: Collate commissioning, compliance and warranty records
8Handover information accepted
- From
- Lead appointed party (main contractor)
- To
- Mechanical Installer
- Hand-off
- Accept
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 6 | Mechanical Installer | Lead appointed party (main contractor) | Submit | Final handover packages through the CDE |
| 7 | Lead appointed party (main contractor) | Mechanical Installer | RejectReturns to stage 4: Collate commissioning, compliance and warranty records | Missing items: amend and resubmit |
| 8 | Lead appointed party (main contractor) | Mechanical Installer | Accept | Handover information accepted |
Checklist
0 of 5 ticked- Upload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – reviewSee the evidence: Upload checked handover information containers to the common data environment for the main contractor's authorization
- Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing - Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment
- Upload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – reviewSee the evidence: Upload checked handover information containers to the common data environment for the main contractor's authorization
- Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing
- Upload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – reviewSee the evidence: Upload checked handover information containers to the common data environment for the main contractor's authorization
- Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information naming conventions and metadata standards
- Exchange Information Requirements (EIR) · Information Use · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Exchange Information Requirements (EIR) - Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization · Action Statement · Suggested – reviewSee the evidence: Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Conduct quality assurance checks on asset data and documentation prior to sharing · Action Statement · Verified
| EIR-04 | Project Manager | Cost Driven Design.\nCost report | level of information need\n<URL LINK>\n | Acceptance criteria\n<URL LINK> | The supporting document outlining the objective of target value design as part of the key purposes of using BIM is available on the CDE as background information\n<URL LINK> | Every second Monday through the design stages of the project.\nFirst exchange DD-MM-YYYY | | EIR-05 | Project Manager | Commissioning report\nDocument building and information is accorInstruction › EIR
See the evidence: Conduct quality assurance checks on asset data and documentation prior to sharing
- Exchange Information Requirements (EIR) · Information Use · Verified
- Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Equipment commissioning report - Provide the digital handover information for installed heating equipment · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Provide the digital handover information for installed heating equipment - Complete commissioning reports using agreed project templates · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Complete commissioning reports using agreed project templates - Capture photographic records of concealed mechanical pipework and installations · Action Statement · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the evidence: Capture photographic records of concealed mechanical pipework and installations
- Equipment commissioning report · Information Use · Verified
Evidence for the flow
- E1
Raise needed changes to the project's information production methods and procedures with the main contractor · Action Statement · Verified
identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement.Instruction
See the full evidence entry - E2
Apply the project's agreed naming conventions and metadata to digital deliverables · Action Statement · Suggested – review
See the full evidence entry - E3
Upload checked handover information containers to the common data environment for the main contractor's authorization · Action Statement · Suggested – review
See the full evidence entry - E4
Equipment commissioning report · Information Use · Verified
All parts of the building and technical equipment will be assessed representatives of the client, the general contractor and the asset team. Relevant hidden constructions and installations will be photo recorded as part of the documentation. * | Template commissioning report agreed and available for project team by DD-MM-YYYY. All commissioning report content ready by DD-MM-YYYY. Commissioning report signed by DD-MM-YYYY. | | EIR-06 | Yes | *Design team deliver technical specification at final sB.2.4.6 BEP – Proposals to amendment project's information standard and project information production methods and procedures › B.2.4.7 BEP – Adopted technologies › B.3 Example 2
See the full evidence entry - E5
Confirm with the main contractor the IT resources, including any CDE app, available for the installer to use on the project · Action Statement · Verified
| Amendments (BIM execution plan) | identify changes that need to be made to the project’s information production methods and procedures and the project’s information standard to best achieve the information requirement. | detail changes that need to be made to the project’s information production methods and procedures and the project’s information standard | | IT Resources (BIM execution plan) | identify Information Technologies Resources available for use on the project | detail the lead appoInstruction
See the full evidence entry - E6
Project information naming conventions and metadata standards · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the full evidence entry
Need this flow in your own tooling? Take an editable copy. It is a one way extract, so edits will not sync back to this report.
Download editable diagramKey actions
Open an Action Statement in the Record using its link icon. Each opens in a new tab.
- 1.
Check own handover information against the in the main contractor's before submitting it to the main contractor for authorization
- 2.
Apply the project's agreed s and metadata to digital deliverables
- 3.
Complete commissioning reports using agreed project templates
- 4.
Collate manufacturer operation and maintenance manuals with warranty certificates
- 5.
Conduct checks on asset data and documentation prior to sharing
- 6.
Upload checked handover s to the for the main contractor's authorization
1 headline and 9 detailed Action Statements are recorded. 6 key detailed actions are shown here, with accepted actions first. Read all Action Statements in the Full Scenario Record (opens in a new tab)
What this role works with
Information Uses recorded for this scenario. Review their suitability for the intended organisation and project.
- 1Equipment commissioning report
- 2Project information naming conventions and metadata standards
- 3Exchange Information Requirements (EIR)
How the scenario unfolds
6 stages · 1 decision with 3 optionsOpen a stage to see its activities and decisions. Guidance links open the matching section of the Record in a new tab.
Review the main contractor's information requirements for the school extension and refurbishment to find out exactly which attributes, serial numbers and certificates are needed for each item of heating equipment before installation starts.
Proposed responsibility: Mechanical Installer
Establish standard data capture sheets and project information naming conventions and metadata standards with the main contractor to enable straightforward CDE submissions without specialist software.
Proposed responsibility: Mechanical Installer
How will installation records be captured on site?
A phone or tablet app.
- Capture records with a phone or tablet app. Record each item's details and photographs on a phone or tablet as it is installed, using a low-cost app that exports in the agreed format.
Rejoin at Capture on-site equipment details and photographs in the Record (opens in a new tab).
Paper sheets, then digitised.
- Record on paper and digitise each week. Keep the familiar paper sheets on site and transfer them into the agreed digital format each week, with photographs filed by equipment reference.
Rejoin at Capture on-site equipment details and photographs in the Record (opens in a new tab).
The main contractor's CDE app.
- Enter records directly in the contractor's CDE app. Use the main contractor's CDE app on site, if it provides one, so records go straight into the project information system.
Rejoin at Capture on-site equipment details and photographs in the Record (opens in a new tab).
Read practical guidance for Agree CDE upload protocols and naming conventions (opens in a new tab)
Record equipment serial numbers, precise locations, and installation dates on a mobile device while fitting heating plant, photographing installed equipment and identification plates.
Proposed responsibility: Mechanical Installer
Read practical guidance for Capture on-site equipment details and photographs (opens in a new tab)
Assemble manufacturer manuals, pressure test results, commissioning records, Building Control (BCAR) ancillary certificates for the mechanical installation, and warranty certificates into structured digital packages for every installed heating item.
Proposed responsibility: Mechanical Installer
Validate digital handover submissions against client acceptance criteria and agreed file naming conventions to ensure all required maintenance and compliance documentation is complete.
Proposed responsibility: Mechanical Installer
Upload the final verified asset packages to the project CDE, meeting the subcontract handover requirements for the school without repeated requests for missing information.
Proposed responsibility: Mechanical Installer
Does the mandate apply?
Ireland – CWMF / Public Works. Applies
Contractors & supply chain on a public works project: the CWMF milestone in force at the 22/10/2026 commencement (over €10m, effective 01/01/2026) covers this project.
Source: CWMF – Public Sector BIM Adoption Timeline. https://cwmf.gov.ie/en/resources/bim/public-sector-bim-adoption-timeline/
Build Digital materials
The material selection and source metadata recorded for this issue. Proposed uses explain how each material supports the workflow; source availability may change.
Supporting materials
This project information standard provides spreadsheet templates and guidance for naming project information in accordance with the Irish National Annex to ISO 19650-2. The support includes the core file-naming workbook, a hyperlink checker, a presentation and a demonstration.
Standard · XLSX
Support the implementation of standard file naming conventions for mechanical handover deliverables.
Provides practical spreadsheet templates, instructions, and demonstration videos tailored to the Irish National Annex of ISO 19650-2, enabling trade subcontractors to generate compliant names without dedicated BIM software.
Included resources
- Project Information Standard – File Naming · primary · XLSX
BD-MAT-3093 · Source revision f3c82554ee73f2db7a730a64ee511aa2d002510d36418243848f00bee156214a
This technology evaluation method provides a structured and transparent approach for assessing digital tools that support Information Management and Building Information Modelling (BIM). It establishes consistent criteria for evaluating functionality, interoperability, usability, compliance with standards such as ISO 19650, and alignment with organisational needs. The method supports objective comparison, informed decision-making, and proportionate investment, ensuring that technology acts as an enabler of defined processes rather than a driver in itself. Overall, it helps organisations select and implement technology solutions that are fit for purpose, scalable, and supportive of long-term Information Management / BIM adoption and continuous improvement.
Protocol · XLSX
Guide the evaluation of proportionate technology options for mobile site capture and CDE participation.
Assists small trade firms in objectively evaluating low-cost mobile applications and CDE field interfaces against usability, ISO 19650 alignment, and cost criteria before deployment.
Included resources
- BIM Technology Evaluation Methodology · primary · XLSX
BD-MAT-3881 · Source revision 3e4ee37a5210f4ea5dcb4a103473d99828b14ea1b12ac4c21a1f56bc244ff410
This delivery-team information management plan provides tenderers with a structured set of templates for responding to a project tender in line with ISO 19650. It covers the delivery team’s information-management function, delivery strategy objectives, federation approach, responsibilities, acceptance criteria, capability, mobilisation and risk planning.
Plan · XLSX
Provide delivery-team templates to understand subcontractor information obligations and delivery planning.
Helps the mechanical contractor understand how their information packages fit into their task information delivery plan, the main contractor's master information delivery plan and BIM execution plan, and the client's acceptance procedures under the Capital Works Management Framework (CWMF).
Included resources
- Information Management Plan – Delivery Team · primary · XLSX
BD-MAT-3121 · Source revision db789419d913153580cb910c037258fcbf872dafd37dcea0d40bca035b865374
- Provide the digital handover information for installed heating equipment
- Check own handover information against the acceptance criteria in the main contractor's exchange information requirements before submitting it to the main contractor for authorization
- Upload checked handover information containers to the common data environment for the main contractor's authorization