Public Sector Project Coordinator
Incorporate the BIM Mandate's information requirements in project management and procurement
Project Coordinator: building the BIM Mandate into a public capital project
The scenario
A Public Sector Project Coordinator responsible for managing a €14 million extension and refurbishment of a post-primary school under the Capital Works Management Framework (CWMF) and the Irish BIM Mandate. The person may be an engineer, architect, project manager or other technical professional working within an Education and Training Board (ETB), a public client organisation. They have experience in project management and public procurement but limited knowledge of BIM and ISO 19650 information management requirements. Their responsibilities extend from project initiation, feasibility and procurement through design, construction and handover. The organisation may have limited in-house information management capability and may rely on external consultants to provide the necessary expertise.
The key challenge is understanding what the BIM Mandate requires the client to do at each project stage and how to incorporate these requirements into normal project management and procurement activities. This includes identifying the information requirements, preparing and evaluating tender documentation, defining information management roles and responsibilities, appointing competent consultants, and ensuring the required information is delivered and reviewed throughout the project. The Project Coordinator also needs to understand how to engage and oversee an Information Manager, whether separately appointed or provided through the project team.
On this project: CWMF Stage 1 began in February 2026. The Coordinator works with the ETB's Information Manager, an architect-led design team that includes a building services engineer, and later the main contractor and its supply chain.
The BIM Mandate is built into normal project management and procurement, and the required information is delivered, reviewed and accepted at each CWMF stage.
How you will know
- The project's information requirements are set before procurement and included in every tender.
- How information management is resourced is decided and recorded, with the reasons.
- Tenders are evaluated against information management criteria, and competent consultants are appointed.
- Information management roles and responsibilities are defined for each appointment.
- Required information is delivered, reviewed and accepted at each CWMF stage through to handover.
A Public Sector Project Coordinator, when initiating a €14 million post-primary school extension and refurbishment, a public capital project that falls under the BIM Mandate, must incorporate the BIM Mandate's information requirements in project management and procurement.
Activity flow diagram
Choose Vertical to follow the flow from top to bottom on a narrow screen.
Scroll sideways to follow the flow. With the diagram focused, use the Left and Right arrow keys.
Scroll sideways to follow the flow. With the diagram focused, use the Left and Right arrow keys.
- Public Sector Project Coordinator
- Information Manager
- Lead appointed party (design team)
- Contractor
- Sanctioning Authority
- Issue
- Submit
- Review
- Reject
- Approve
- Inform
- Returns work to amend and resubmit
Explore the flow by stage
8 stages · 1 decision with 4 optionsChoose a stage to see what each party does in it, the hand-offs between them and any decision that follows. A decision's options are listed under it. The hand-off numbers match the numbered arrows on the diagram.
Each stage below shows what each party does in it, the hand-offs between them and any decision that follows. A decision's options are listed under it. The hand-off numbers match the numbered arrows on the diagram. Each stage's checklist is in the Full Scenario Record.
Decision after stage 1Who will perform the client information management function?One option applies.
Stage 1: Confirm the BIM requirements that apply to the project
Public Sector Project Coordinator
Confirm that the €14 million school project falls under the CWMF BIM requirements for both the design team and contractor appointments, and record it in the Project Execution Plan.
Responsible: Public Sector Project Coordinator
Who does what at this stage
Public Sector Project Coordinator
The role
Carries out stage 1
Confirm the BIM requirements that apply to the project
Then decides: Who will perform the client information management function?
Information Manager
A function the scenario names
No part in this stage.
Lead appointed party (design team)
ISO 19650 party
No part in this stage.
Contractor
ISO 19650 party
No part in this stage.
Sanctioning Authority
A governance body in the framework
No part in this stage.
No part in this stage: Information Manager, Lead appointed party (design team), Contractor, Sanctioning Authority.
Hand-offs at this stage
No hand-offs at this stage.
Decision: Who will perform the client information management function?
After stage 1: Confirm the BIM requirements that apply to the project. One option applies. Marks show how well each option meets a criterion. They are not scores, and they are not added up or ranked.
| Criterion | Option 1.1An in-house nominee | Option 1.2An independent third-party consultant | Option 1.3Delegated to the lead appointed party | Option 1.4Hybrid: in-house owner with external support |
|---|---|---|---|---|
| Client alignment and internal controlDoes this approach ensure direct client control and continuity across CWMF project decision points? Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E4 Review prospective appointed parties; E6 Incorporate the BIM Mandate's information requirements in project management and procurement
| +Strong Direct internal ownership guarantees alignment with CWMF decision gates and long-term asset needs. Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E4 Review prospective appointed parties
| ~Depends Requires rigorous briefing and ongoing coordination to align external advisers with CWMF procedures. Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E6 Incorporate the BIM Mandate's information requirements in project management and procurement
| ~Depends Client control may weaken if decision-point governance is absorbed into the lead designer work plan. Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E4 Review prospective appointed parties
| +Strong An in-house lead ensures direct accountability while external support provides technical rigor. Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E4 Review prospective appointed parties
|
| Independence and conflict mitigationDoes the arrangement maintain independent oversight of delivery team information deliverables? Evidence: E4 Review prospective appointed parties
| +Strong Internal staff maintain complete independence from appointed delivery teams. Evidence: E4 Review prospective appointed parties
| +Strong Third-party specialists operate independently from appointed design teams and contractors. Evidence: E4 Review prospective appointed parties
| –Weak Delegating client-side acceptance to the design lead creates an inherent conflict of interest. Evidence: E4 Review prospective appointed parties
| +Strong External advice remains distinct from design team delivery, preserving objective review. Evidence: E4 Review prospective appointed parties
|
| Technical capability and resource demandCan the function be delivered within existing public sector capacity without disproportionate strain? Evidence: E4 Review prospective appointed parties
| ~Depends Success depends on existing public sector staff having sufficient ISO 19650 technical capability and time. Evidence: E4 Review prospective appointed parties
| +Strong Brings ready-made specialist expertise without overburdening internal public sector staff. Evidence: E4 Review prospective appointed parties
| +Strong Minimises direct client operational workload by transferring technical duties to the design team. Evidence: E4 Review prospective appointed parties
| +Strong Combines client governance with targeted external technical capacity, mitigating internal strain. Evidence: E4 Review prospective appointed parties
|
Option 1.1
An in-house nominee
- Option 1.1: Nominate an in-house information manager
Rejoins at stage 2: Set the project and asset information requirements.
- Client alignment and internal control
- +StrongDirect internal ownership guarantees alignment with CWMF decision gates and long-term asset needs.
Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E4 Review prospective appointed parties
Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryFacilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryEstablish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryReview prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- Independence and conflict mitigation
- +StrongInternal staff maintain complete independence from appointed delivery teams.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- Technical capability and resource demand
- ~DependsSuccess depends on existing public sector staff having sufficient ISO 19650 technical capability and time.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
Consequences
- The appointing party maintains immediate oversight over information container acceptance without third-party procurement delays.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- Internal resource constraints may arise if staff lack sufficient technical BIM management capacity.
Evidence: E5 Align information management processes with the Infrastructure Guidelines and CWMF
Align information management processes with the Infrastructure Guidelines and CWMF · Action Statement · Verified
The Senior Information Manager (BIM) is responsible for leading and overseeing Information Management on complex, high-value, or high-risk projects, or across multiple concurrent projects. This role ensures that Information Management processes are fully aligned with the CWMF BIM requirement (Irish BIM mandate) and also align with the ISO 19650 series, the Capital Works Management Framework (CWMF), Infrastructure Guidelines, and client asset information requirements. The Senior Information Manag
See the full evidence entry
- Client retains immediate authority and oversight over information management throughout project stages.
Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E4 Review prospective appointed parties
Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryFacilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryEstablish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryReview prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- In-house resources may face significant strain if public sector staff lack specialised ISO 19650 experience.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E4 Review prospective appointed parties; E5 Align information management processes with the Infrastructure Guidelines and CWMF
Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryFacilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryEstablish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryReview prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entryAlign information management processes with the Infrastructure Guidelines and CWMF · Action Statement · Verified
The Senior Information Manager (BIM) is responsible for leading and overseeing Information Management on complex, high-value, or high-risk projects, or across multiple concurrent projects. This role ensures that Information Management processes are fully aligned with the CWMF BIM requirement (Irish BIM mandate) and also align with the ISO 19650 series, the Capital Works Management Framework (CWMF), Infrastructure Guidelines, and client asset information requirements. The Senior Information Manag
See the full evidence entry
Option 1.2
An independent third-party consultant
- Option 1.2: Appoint an independent information management consultant
Rejoins at stage 2: Set the project and asset information requirements.
- Client alignment and internal control
- ~DependsRequires rigorous briefing and ongoing coordination to align external advisers with CWMF procedures.
Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E6 Incorporate the BIM Mandate's information requirements in project management and procurement
Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryFacilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryEstablish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryIncorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the full evidence entry
- Independence and conflict mitigation
- +StrongThird-party specialists operate independently from appointed design teams and contractors.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- Technical capability and resource demand
- +StrongBrings ready-made specialist expertise without overburdening internal public sector staff.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
Consequences
- External procurement must be completed to appoint the consultant before project information requirements are finalized.
Evidence: E4 Review prospective appointed parties; E7 Tender and procurement documentation; E8 Tender evaluation criteria for information management; E9 Information delivery risk assessment; E10 Establish the project common data environment that every delivery team will use
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entryTender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryTender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryInformation delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryEstablish the project common data environment that every delivery team will use · Action Statement · Suggested – review
See the full evidence entry
- Specialized ISO 19650 advice is secured for tender EIR and CDE workflow preparation.
Evidence: E7 Tender and procurement documentation; E8 Tender evaluation criteria for information management; E9 Information delivery risk assessment; E10 Establish the project common data environment that every delivery team will use
Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryTender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryInformation delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryEstablish the project common data environment that every delivery team will use · Action Statement · Suggested – review
See the full evidence entry
- High-level technical expertise is secured without overextending internal public sector resources.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- Additional procurement costs and management effort are required to appoint and monitor the consultant.
Evidence: E4 Review prospective appointed parties; E6 Incorporate the BIM Mandate's information requirements in project management and procurement
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entryIncorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the full evidence entry
Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E6 Incorporate the BIM Mandate's information requirements in project management and procurement; E4 Review prospective appointed parties; E7 Tender and procurement documentation; E8 Tender evaluation criteria for information management; E9 Information delivery risk assessment; E10 Establish the project common data environment that every delivery team will use
Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryFacilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryEstablish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryIncorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the full evidence entryReview prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entryTender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryTender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryInformation delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryEstablish the project common data environment that every delivery team will use · Action Statement · Suggested – review
See the full evidence entry
Option 1.3
Delegated to the lead appointed party
- Option 1.3: Assign client-side tasks to the design team lead
Rejoins at stage 2: Set the project and asset information requirements.
- Client alignment and internal control
- ~DependsClient control may weaken if decision-point governance is absorbed into the lead designer work plan.
Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E4 Review prospective appointed parties
Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryFacilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryEstablish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryReview prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- Independence and conflict mitigation
- –WeakDelegating client-side acceptance to the design lead creates an inherent conflict of interest.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- Technical capability and resource demand
- +StrongMinimises direct client operational workload by transferring technical duties to the design team.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
Consequences
- Verification of design outputs and model federation is handled by the party producing them.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- Client-specific gate deliverables under CWMF may lack independent quality validation.
Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points
Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryFacilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryEstablish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entry
- Client risks compromised oversight when the lead appointed party checks its own information models.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- Internal public sector administrative effort is reduced during day-to-day model coordination.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E4 Review prospective appointed parties
Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryFacilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryEstablish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryReview prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
Option 1.4
Hybrid: in-house owner with external support
- Option 1.4: Name an in-house owner and buy in defined support
Rejoins at stage 2: Set the project and asset information requirements.
- Client alignment and internal control
- +StrongAn in-house lead ensures direct accountability while external support provides technical rigor.
Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E4 Review prospective appointed parties
Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryFacilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryEstablish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryReview prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- Independence and conflict mitigation
- +StrongExternal advice remains distinct from design team delivery, preserving objective review.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- Technical capability and resource demand
- +StrongCombines client governance with targeted external technical capacity, mitigating internal strain.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
Consequences
- The public sector coordinator retains decision authority while technical EIR checks are supported by specialists.
Evidence: E5 Align information management processes with the Infrastructure Guidelines and CWMF; E7 Tender and procurement documentation; E8 Tender evaluation criteria for information management; E9 Information delivery risk assessment; E10 Establish the project common data environment that every delivery team will use
Align information management processes with the Infrastructure Guidelines and CWMF · Action Statement · Verified
The Senior Information Manager (BIM) is responsible for leading and overseeing Information Management on complex, high-value, or high-risk projects, or across multiple concurrent projects. This role ensures that Information Management processes are fully aligned with the CWMF BIM requirement (Irish BIM mandate) and also align with the ISO 19650 series, the Capital Works Management Framework (CWMF), Infrastructure Guidelines, and client asset information requirements. The Senior Information Manag
See the full evidence entryTender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryTender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryInformation delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryEstablish the project common data environment that every delivery team will use · Action Statement · Suggested – review
See the full evidence entry
- Requires clear definition of responsibilities between internal staff and external support advisors.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- Client retains strategic governance while filling technical competency gaps with specialist support.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
- Clear division of responsibilities is required between the in-house owner and the external adviser.
Evidence: E4 Review prospective appointed parties
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry
Evidence: E1 Definitive Project Brief; E2 Facilitate information requirements workshops with project stakeholders; E3 Establish the Project Information Requirements for key project decision points; E4 Review prospective appointed parties; E5 Align information management processes with the Infrastructure Guidelines and CWMF; E7 Tender and procurement documentation; E8 Tender evaluation criteria for information management; E9 Information delivery risk assessment; E10 Establish the project common data environment that every delivery team will use
Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryFacilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryEstablish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entryReview prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entryAlign information management processes with the Infrastructure Guidelines and CWMF · Action Statement · Verified
The Senior Information Manager (BIM) is responsible for leading and overseeing Information Management on complex, high-value, or high-risk projects, or across multiple concurrent projects. This role ensures that Information Management processes are fully aligned with the CWMF BIM requirement (Irish BIM mandate) and also align with the ISO 19650 series, the Capital Works Management Framework (CWMF), Infrastructure Guidelines, and client asset information requirements. The Senior Information Manag
See the full evidence entryTender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryTender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryInformation delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entryEstablish the project common data environment that every delivery team will use · Action Statement · Suggested – review
See the full evidence entry
Checklist
0 of 8 ticked- Integrate information management milestones into the Project Execution Plan · Action Statement · Verified
| Document information | | | |---|---|---| | Title | Guidance | Information | | Project | What Project is the Plan for? | Project Name | | Title | What is the title of this document? | Information Management Plan - Delivery Team | | Quality | Who performed the quality check on this document? | Checked PL / Reviewed PL / Approved PL | | Document File Naming | What is this document's file naming? | InformationManagementPlan-DeliveryTeam.xlsx | | Version | What is this document's current version? |Instruction
See the evidence: Integrate information management milestones into the Project Execution Plan - Project Execution Plan (PEP) · Information Use · Verified
The Project Coordinator (continued) Responsibilities The Project Coordinator is responsible for the following: - Managing the Project Programme; - Developing the Project Execution Plan; - Approving interim reports and ensuring that any project changes are evaluated and reported; - Ensuring the development of the Definitive Project Brief; - Ensuring that all stakeholders (including end users) are involved with and committed to the project; - Managing project reviews and obtaining approval from th1.4 Managing the Project Programme, Continued, Continued › 3.2 Management Team: Roles and Responsibilities, Continued
See the evidence: Project Execution Plan (PEP)
- Integrate information management milestones into the Project Execution Plan · Action Statement · Verified
- Establish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Establish the Project Information Requirements for key project decision points - Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Definitive Project Brief - Facilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Facilitate information requirements workshops with project stakeholders - Project Information Requirements (PIR) · Information Use · Verified
- Act as the lead project information manager for assigned projects, ensuring compliance with ISO 19650 and CWMF/ Infrastructure Guidelines deliverables. - Develop and implement the project's Information Management Plan (IM Plan), including processes for information production, validation, and exchange. - Ensure compliance with exchange information requirements (EIR), asset information requirements (AIR), and project information requirements (PIR). - Manage the CDE, overseeing information workfl
See the evidence: Project Information Requirements (PIR)
- Establish the Project Information Requirements for key project decision points · Action Statement · Verified
- Align information management processes with the Infrastructure Guidelines and CWMF · Action Statement · Verified
The Senior Information Manager (BIM) is responsible for leading and overseeing Information Management on complex, high-value, or high-risk projects, or across multiple concurrent projects. This role ensures that Information Management processes are fully aligned with the CWMF BIM requirement (Irish BIM mandate) and also align with the ISO 19650 series, the Capital Works Management Framework (CWMF), Infrastructure Guidelines, and client asset information requirements. The Senior Information Manag
See the evidence: Align information management processes with the Infrastructure Guidelines and CWMF - Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender and procurement documentation - Tender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender evaluation criteria for information management - Information delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Information delivery risk assessment
- Align information management processes with the Infrastructure Guidelines and CWMF · Action Statement · Verified
- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Incorporate the BIM Mandate's information requirements in project management and procurement - Capital Works Management Framework (CWMF) guidance and templates · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Capital Works Management Framework (CWMF) guidance and templates
- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
- Nominate internal individuals or appoint third-party support to undertake the information management function · Action Statement · Verified
The appointing party shall nominate individuals from within its organization to undertake the information management function. Alternatively, the appointing party can appoint a prospective lead appointed party or a third party to undertake all or part of the information management function. In which case the appointing party shall establish a scope of services for that appointment. In doing this, the appointing party shall consider the tasks that the prospective lead appointed party or third par5.1.1 Appoint individuals to undertake the information management function
See the evidence: Nominate internal individuals or appoint third-party support to undertake the information management function - Allocate information management functions across internal staff or external appointments · Action Statement · Verified
Clarity of functions, responsibility, authority and the scope of any task are essential aspects of effective information management. Functions should be embedded into appointments, either through a specific schedule of services or by referring to more general obligations. 18 © ISO 2018 – All rights reserved --- ISO 19650-1:2018(E) This document identifies the types of information management functions that should be considered and their responsibilities, and should be read in conjunction with oth6.3.1 General principles › 7 Project and asset information management functions › 7.1 Principles
See the evidence: Allocate information management functions across internal staff or external appointments
- Nominate internal individuals or appoint third-party support to undertake the information management function · Action Statement · Verified
- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Incorporate the BIM Mandate's information requirements in project management and procurement - Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender and procurement documentation - Exchange Information Requirements (EIR) · Information Use · Verified
- Act as the lead project information manager for assigned projects, ensuring compliance with ISO 19650 and CWMF/ Infrastructure Guidelines deliverables. - Develop and implement the project's Information Management Plan (IM Plan), including processes for information production, validation, and exchange. - Ensure compliance with exchange information requirements (EIR), asset information requirements (AIR), and project information requirements (PIR). - Manage the CDE, overseeing information workfl
See the evidence: Exchange Information Requirements (EIR) - Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the evidence: Review prospective appointed parties - Tender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender evaluation criteria for information management - Information delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Information delivery risk assessment
- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
- Align information management processes with the Infrastructure Guidelines and CWMF · Action Statement · Verified
The Senior Information Manager (BIM) is responsible for leading and overseeing Information Management on complex, high-value, or high-risk projects, or across multiple concurrent projects. This role ensures that Information Management processes are fully aligned with the CWMF BIM requirement (Irish BIM mandate) and also align with the ISO 19650 series, the Capital Works Management Framework (CWMF), Infrastructure Guidelines, and client asset information requirements. The Senior Information Manag
See the evidence: Align information management processes with the Infrastructure Guidelines and CWMF - Capital Works Management Framework (CWMF) guidance and templates · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Capital Works Management Framework (CWMF) guidance and templates - Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the evidence: Review prospective appointed parties - Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Incorporate the BIM Mandate's information requirements in project management and procurement
- Align information management processes with the Infrastructure Guidelines and CWMF · Action Statement · Verified
- Establish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Establish the Project Information Requirements for key project decision points - Project Information Requirements (PIR) · Information Use · Verified
- Act as the lead project information manager for assigned projects, ensuring compliance with ISO 19650 and CWMF/ Infrastructure Guidelines deliverables. - Develop and implement the project's Information Management Plan (IM Plan), including processes for information production, validation, and exchange. - Ensure compliance with exchange information requirements (EIR), asset information requirements (AIR), and project information requirements (PIR). - Manage the CDE, overseeing information workfl
See the evidence: Project Information Requirements (PIR) - Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Definitive Project Brief - Facilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Facilitate information requirements workshops with project stakeholders - Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the evidence: Review prospective appointed parties
- Establish the Project Information Requirements for key project decision points · Action Statement · Verified
Option 1.1: Nominate an in-house information manager
Public Sector Project Coordinator · an option of the decision after stage 1: Confirm the BIM requirements that apply to the project
Name a member of staff with the competence and time to perform the client information management function, with a written scope and delegated authority.
Responsible: Public Sector Project Coordinator
Who does what at this stage
Public Sector Project Coordinator
The role
Carries out option 1.1
Nominate an in-house information manager
Information Manager
A function the scenario names
No part in this stage.
Lead appointed party (design team)
ISO 19650 party
No part in this stage.
Contractor
ISO 19650 party
No part in this stage.
Sanctioning Authority
A governance body in the framework
No part in this stage.
No part in this stage: Information Manager, Lead appointed party (design team), Contractor, Sanctioning Authority.
Hand-offs at this stage
No hand-offs at this stage.
Option 1.2: Appoint an independent information management consultant
Public Sector Project Coordinator · an option of the decision after stage 1: Confirm the BIM requirements that apply to the project
Appoint a consultant under its own COE1 appointment, before the design team tender, so the EIR and CDE are ready to issue.
Responsible: Public Sector Project Coordinator
Who does what at this stage
Public Sector Project Coordinator
The role
Carries out option 1.2
Appoint an independent information management consultant
Information Manager
A function the scenario names
No part in this stage.
Lead appointed party (design team)
ISO 19650 party
No part in this stage.
Contractor
ISO 19650 party
No part in this stage.
Sanctioning Authority
A governance body in the framework
No part in this stage.
No part in this stage: Information Manager, Lead appointed party (design team), Contractor, Sanctioning Authority.
Hand-offs at this stage
No hand-offs at this stage.
Option 1.3: Assign client-side tasks to the design team lead
Public Sector Project Coordinator · an option of the decision after stage 1: Confirm the BIM requirements that apply to the project
Write client-side information tasks into the design team scope, with different individuals for client-side and delivery-side work, and keep acceptance yourself.
Responsible: Public Sector Project Coordinator
Who does what at this stage
Public Sector Project Coordinator
The role
Carries out option 1.3
Assign client-side tasks to the design team lead
Information Manager
A function the scenario names
No part in this stage.
Lead appointed party (design team)
ISO 19650 party
No part in this stage.
Contractor
ISO 19650 party
No part in this stage.
Sanctioning Authority
A governance body in the framework
No part in this stage.
No part in this stage: Information Manager, Lead appointed party (design team), Contractor, Sanctioning Authority.
Hand-offs at this stage
No hand-offs at this stage.
Option 1.4: Name an in-house owner and buy in defined support
Public Sector Project Coordinator · an option of the decision after stage 1: Confirm the BIM requirements that apply to the project
Name an accountable in-house owner and appoint external support for defined tasks, building in-house capability for later projects.
Responsible: Public Sector Project Coordinator
Who does what at this stage
Public Sector Project Coordinator
The role
Carries out option 1.4
Name an in-house owner and buy in defined support
Information Manager
A function the scenario names
No part in this stage.
Lead appointed party (design team)
ISO 19650 party
No part in this stage.
Contractor
ISO 19650 party
No part in this stage.
Sanctioning Authority
A governance body in the framework
No part in this stage.
No part in this stage: Information Manager, Lead appointed party (design team), Contractor, Sanctioning Authority.
Hand-offs at this stage
No hand-offs at this stage.
Stage 2: Set the project and asset information requirements
Public Sector Project Coordinator
Turn each key decision point into the questions you need answered, and capture what the school will need to operate and maintain the building.
Responsible: Public Sector Project Coordinator
Who does what at this stage
Public Sector Project Coordinator
The role
Carries out stage 2
Set the project and asset information requirements
Information Manager
A function the scenario names
No part in this stage.
Lead appointed party (design team)
ISO 19650 party
No part in this stage.
Contractor
ISO 19650 party
No part in this stage.
Sanctioning Authority
A governance body in the framework
No part in this stage.
No part in this stage: Information Manager, Lead appointed party (design team), Contractor, Sanctioning Authority.
Hand-offs at this stage
No hand-offs at this stage.
Checklist
0 of 8 ticked- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Incorporate the BIM Mandate's information requirements in project management and procurement - Establish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Establish the Project Information Requirements for key project decision points - Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Definitive Project Brief - Facilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Facilitate information requirements workshops with project stakeholders - Project Execution Plan (PEP) · Information Use · Verified
The Project Coordinator (continued) Responsibilities The Project Coordinator is responsible for the following: - Managing the Project Programme; - Developing the Project Execution Plan; - Approving interim reports and ensuring that any project changes are evaluated and reported; - Ensuring the development of the Definitive Project Brief; - Ensuring that all stakeholders (including end users) are involved with and committed to the project; - Managing project reviews and obtaining approval from th1.4 Managing the Project Programme, Continued, Continued › 3.2 Management Team: Roles and Responsibilities, Continued
See the evidence: Project Execution Plan (PEP) - Delivery team capability and capacity assessment · Information Use · Verified
The Project Coordinator (continued) Responsibilities The Project Coordinator is responsible for the following: - Managing the Project Programme; - Developing the Project Execution Plan; - Approving interim reports and ensuring that any project changes are evaluated and reported; - Ensuring the development of the Definitive Project Brief; - Ensuring that all stakeholders (including end users) are involved with and committed to the project; - Managing project reviews and obtaining approval from th1.4 Managing the Project Programme, Continued, Continued › 3.2 Management Team: Roles and Responsibilities, Continued
See the evidence: Delivery team capability and capacity assessment
- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
- Define Project Information Requirements aligned with the Capital Works Management Framework · Action Statement · Verified
- Act as the lead project information manager for assigned projects, ensuring compliance with ISO 19650 and CWMF/ Infrastructure Guidelines deliverables. - Develop and implement the project's Information Management Plan (IM Plan), including processes for information production, validation, and exchange. - Ensure compliance with exchange information requirements (EIR), asset information requirements (AIR), and project information requirements (PIR). - Manage the CDE, overseeing information workfl
See the evidence: Define Project Information Requirements aligned with the Capital Works Management Framework - Establish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Establish the Project Information Requirements for key project decision points - Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Definitive Project Brief - Facilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Facilitate information requirements workshops with project stakeholders - Project Information Requirements (PIR) · Information Use · Verified
- Act as the lead project information manager for assigned projects, ensuring compliance with ISO 19650 and CWMF/ Infrastructure Guidelines deliverables. - Develop and implement the project's Information Management Plan (IM Plan), including processes for information production, validation, and exchange. - Ensure compliance with exchange information requirements (EIR), asset information requirements (AIR), and project information requirements (PIR). - Manage the CDE, overseeing information workfl
See the evidence: Project Information Requirements (PIR)
- Define Project Information Requirements aligned with the Capital Works Management Framework · Action Statement · Verified
- Align information delivery milestones with Capital Works Management Framework project reviews · Action Statement · Verified
| – the appointing party’s exchange information requirements; | | EIR (Exchange Information Requirements) | | – the relevant reference information and shared resources (within the project’s common data environment); | | Supporting information | | – the tender response requirements and evaluation criteria (if applicable); | | Acceptance criteria | | – the project information delivery milestones; | | Evaluation criteria | | – the project’s information standard; | | Acceptance criteria | | – the prInstruction
See the evidence: Align information delivery milestones with Capital Works Management Framework project reviews - Capital Works Management Framework (CWMF) guidance and templates · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Capital Works Management Framework (CWMF) guidance and templates - Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Definitive Project Brief - Facilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Facilitate information requirements workshops with project stakeholders - Establish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Establish the Project Information Requirements for key project decision points - Project information standard and protocol · Information Use · Verified
| – the appointing party’s exchange information requirements; | | EIR (Exchange Information Requirements) | | – the relevant reference information and shared resources (within the project’s common data environment); | | Supporting information | | – the tender response requirements and evaluation criteria (if applicable); | | Acceptance criteria | | – the project information delivery milestones; | | Evaluation criteria | | – the project’s information standard; | | Acceptance criteria | | – the prInstruction
See the evidence: Project information standard and protocol
- Align information delivery milestones with Capital Works Management Framework project reviews · Action Statement · Verified
- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Incorporate the BIM Mandate's information requirements in project management and procurement - Define Project Information Requirements aligned with the Capital Works Management Framework · Action Statement · Verified
- Act as the lead project information manager for assigned projects, ensuring compliance with ISO 19650 and CWMF/ Infrastructure Guidelines deliverables. - Develop and implement the project's Information Management Plan (IM Plan), including processes for information production, validation, and exchange. - Ensure compliance with exchange information requirements (EIR), asset information requirements (AIR), and project information requirements (PIR). - Manage the CDE, overseeing information workfl
See the evidence: Define Project Information Requirements aligned with the Capital Works Management Framework
- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
- Define Project Information Requirements aligned with the Capital Works Management Framework · Action Statement · Verified
- Act as the lead project information manager for assigned projects, ensuring compliance with ISO 19650 and CWMF/ Infrastructure Guidelines deliverables. - Develop and implement the project's Information Management Plan (IM Plan), including processes for information production, validation, and exchange. - Ensure compliance with exchange information requirements (EIR), asset information requirements (AIR), and project information requirements (PIR). - Manage the CDE, overseeing information workfl
See the evidence: Define Project Information Requirements aligned with the Capital Works Management Framework - Align information delivery milestones with Capital Works Management Framework project reviews · Action Statement · Verified
| – the appointing party’s exchange information requirements; | | EIR (Exchange Information Requirements) | | – the relevant reference information and shared resources (within the project’s common data environment); | | Supporting information | | – the tender response requirements and evaluation criteria (if applicable); | | Acceptance criteria | | – the project information delivery milestones; | | Evaluation criteria | | – the project’s information standard; | | Acceptance criteria | | – the prInstruction
See the evidence: Align information delivery milestones with Capital Works Management Framework project reviews - Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Definitive Project Brief - Facilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Facilitate information requirements workshops with project stakeholders - Establish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Establish the Project Information Requirements for key project decision points - Capital Works Management Framework (CWMF) guidance and templates · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Capital Works Management Framework (CWMF) guidance and templates
- Define Project Information Requirements aligned with the Capital Works Management Framework · Action Statement · Verified
- Confirm the Asset Information Requirements that the exchange information requirements must deliver at handover · Action Statement · Suggested – reviewSee the evidence: Confirm the Asset Information Requirements that the exchange information requirements must deliver at handover
- Asset Information Requirements (AIR) · Information Use · Verified
- Act as the lead project information manager for assigned projects, ensuring compliance with ISO 19650 and CWMF/ Infrastructure Guidelines deliverables. - Develop and implement the project's Information Management Plan (IM Plan), including processes for information production, validation, and exchange. - Ensure compliance with exchange information requirements (EIR), asset information requirements (AIR), and project information requirements (PIR). - Manage the CDE, overseeing information workfl
See the evidence: Asset Information Requirements (AIR)
- Confirm the Asset Information Requirements that the exchange information requirements must deliver at handover · Action Statement · Suggested – reviewSee the evidence: Confirm the Asset Information Requirements that the exchange information requirements must deliver at handover
- Asset Information Requirements (AIR) · Information Use · Verified
- Act as the lead project information manager for assigned projects, ensuring compliance with ISO 19650 and CWMF/ Infrastructure Guidelines deliverables. - Develop and implement the project's Information Management Plan (IM Plan), including processes for information production, validation, and exchange. - Ensure compliance with exchange information requirements (EIR), asset information requirements (AIR), and project information requirements (PIR). - Manage the CDE, overseeing information workfl
See the evidence: Asset Information Requirements (AIR)
- Facilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Facilitate information requirements workshops with project stakeholders - Project Execution Plan (PEP) · Information Use · Verified
The Project Coordinator (continued) Responsibilities The Project Coordinator is responsible for the following: - Managing the Project Programme; - Developing the Project Execution Plan; - Approving interim reports and ensuring that any project changes are evaluated and reported; - Ensuring the development of the Definitive Project Brief; - Ensuring that all stakeholders (including end users) are involved with and committed to the project; - Managing project reviews and obtaining approval from th1.4 Managing the Project Programme, Continued, Continued › 3.2 Management Team: Roles and Responsibilities, Continued
See the evidence: Project Execution Plan (PEP) - Delivery team capability and capacity assessment · Information Use · Verified
The Project Coordinator (continued) Responsibilities The Project Coordinator is responsible for the following: - Managing the Project Programme; - Developing the Project Execution Plan; - Approving interim reports and ensuring that any project changes are evaluated and reported; - Ensuring the development of the Definitive Project Brief; - Ensuring that all stakeholders (including end users) are involved with and committed to the project; - Managing project reviews and obtaining approval from th1.4 Managing the Project Programme, Continued, Continued › 3.2 Management Team: Roles and Responsibilities, Continued
See the evidence: Delivery team capability and capacity assessment
- Facilitate information requirements workshops with project stakeholders · Action Statement · Verified
Stage 3: Approve the information standard, protocol and CDE rules
Public Sector Project Coordinator
Approve the information standard, production methods, protocol and common data environment arrangements that every appointment will follow.
Responsible: Public Sector Project Coordinator
Who does what at this stage
Public Sector Project Coordinator
The role
Carries out stage 3
Approve the information standard, protocol and CDE rules
- Receives 1: Draft information standard, protocol and CDE rules from Information Manager (submit)
Information Manager
A function the scenario names
- Sends 1: Draft information standard, protocol and CDE rules to Public Sector Project Coordinator (submit)
Lead appointed party (design team)
ISO 19650 party
No part in this stage.
Contractor
ISO 19650 party
No part in this stage.
Sanctioning Authority
A governance body in the framework
No part in this stage.
No part in this stage: Lead appointed party (design team), Contractor, Sanctioning Authority.
Hand-offs at this stage
1Draft information standard, protocol and CDE rules
- From
- Information Manager
- To
- Public Sector Project Coordinator
- Hand-off
- Submit
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 1 | Information Manager | Public Sector Project Coordinator | Submit | Draft information standard, protocol and CDE rules |
Checklist
0 of 8 ticked- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Incorporate the BIM Mandate's information requirements in project management and procurement - Align information management processes with the Infrastructure Guidelines and CWMF · Action Statement · Verified
The Senior Information Manager (BIM) is responsible for leading and overseeing Information Management on complex, high-value, or high-risk projects, or across multiple concurrent projects. This role ensures that Information Management processes are fully aligned with the CWMF BIM requirement (Irish BIM mandate) and also align with the ISO 19650 series, the Capital Works Management Framework (CWMF), Infrastructure Guidelines, and client asset information requirements. The Senior Information Manag
See the evidence: Align information management processes with the Infrastructure Guidelines and CWMF - Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender and procurement documentation - Information delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Information delivery risk assessment - Establish the project common data environment that every delivery team will use · Action Statement · Suggested – reviewSee the evidence: Establish the project common data environment that every delivery team will use
- Project information standard and protocol · Information Use · Verified
| – the appointing party’s exchange information requirements; | | EIR (Exchange Information Requirements) | | – the relevant reference information and shared resources (within the project’s common data environment); | | Supporting information | | – the tender response requirements and evaluation criteria (if applicable); | | Acceptance criteria | | – the project information delivery milestones; | | Evaluation criteria | | – the project’s information standard; | | Acceptance criteria | | – the prInstruction
See the evidence: Project information standard and protocol
- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
- Align information delivery milestones with Capital Works Management Framework project reviews · Action Statement · Verified
| – the appointing party’s exchange information requirements; | | EIR (Exchange Information Requirements) | | – the relevant reference information and shared resources (within the project’s common data environment); | | Supporting information | | – the tender response requirements and evaluation criteria (if applicable); | | Acceptance criteria | | – the project information delivery milestones; | | Evaluation criteria | | – the project’s information standard; | | Acceptance criteria | | – the prInstruction
See the evidence: Align information delivery milestones with Capital Works Management Framework project reviews - Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender and procurement documentation - Tender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender evaluation criteria for information management - Information delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Information delivery risk assessment
- Align information delivery milestones with Capital Works Management Framework project reviews · Action Statement · Verified
- Embed information management functions into professional services and works appointments · Action Statement · Suggested – reviewSee the evidence: Embed information management functions into professional services and works appointments
- Identify types of information management functions · Action Statement · Verified
identifies the types of information management functions that should be considered6.3.1 General principles › 7 Project and asset information management functions › 7.1 Principles
See the evidence: Identify types of information management functions - Allocate information management functions across internal staff or external appointments · Action Statement · Verified
Clarity of functions, responsibility, authority and the scope of any task are essential aspects of effective information management. Functions should be embedded into appointments, either through a specific schedule of services or by referring to more general obligations. 18 © ISO 2018 – All rights reserved --- ISO 19650-1:2018(E) This document identifies the types of information management functions that should be considered and their responsibilities, and should be read in conjunction with oth6.3.1 General principles › 7 Project and asset information management functions › 7.1 Principles
See the evidence: Allocate information management functions across internal staff or external appointments - Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender and procurement documentation - Tender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender evaluation criteria for information management - Information management scope of services · Information Use · Verified
The appointing party shall nominate individuals from within its organization to undertake the information management function. Alternatively, the appointing party can appoint a prospective lead appointed party or a third party to undertake all or part of the information management function. In which case the appointing party shall establish a scope of services for that appointment. In doing this, the appointing party shall consider the tasks that the prospective lead appointed party or third par5.1.1 Appoint individuals to undertake the information management function
See the evidence: Information management scope of services
- Define information management roles and delegated responsibilities across project appointments · Action Statement · Verified
The appointing party shall nominate individuals from within its organization to undertake the information management function. Alternatively, the appointing party can appoint a prospective lead appointed party or a third party to undertake all or part of the information management function. In which case the appointing party shall establish a scope of services for that appointment. In doing this, the appointing party shall consider the tasks that the prospective lead appointed party or third par5.1.1 Appoint individuals to undertake the information management function
See the evidence: Define information management roles and delegated responsibilities across project appointments - Define the specific function of information facilitation or information process management · Action Statement · Verified
The complexity of project information management functions should reflect the extent and complexity of project information. It is important that functions are assigned at all times during the project, but the sequence of appointments and their scope should reflect the procurement route being used. Project information management involves leadership in establishing the project's information standard, the production methods and procedures, and the project's CDE. The appointing party allocates respo6.3.1 General principles › 7.3 Project information management functions
See the evidence: Define the specific function of information facilitation or information process management - Embed information management functions into professional services and works appointments · Action Statement · Suggested – reviewSee the evidence: Embed information management functions into professional services and works appointments
- Identify types of information management functions · Action Statement · Verified
identifies the types of information management functions that should be considered6.3.1 General principles › 7 Project and asset information management functions › 7.1 Principles
See the evidence: Identify types of information management functions - Allocate information management functions across internal staff or external appointments · Action Statement · Verified
Clarity of functions, responsibility, authority and the scope of any task are essential aspects of effective information management. Functions should be embedded into appointments, either through a specific schedule of services or by referring to more general obligations. 18 © ISO 2018 – All rights reserved --- ISO 19650-1:2018(E) This document identifies the types of information management functions that should be considered and their responsibilities, and should be read in conjunction with oth6.3.1 General principles › 7 Project and asset information management functions › 7.1 Principles
See the evidence: Allocate information management functions across internal staff or external appointments - Information management scope of services · Information Use · Verified
The appointing party shall nominate individuals from within its organization to undertake the information management function. Alternatively, the appointing party can appoint a prospective lead appointed party or a third party to undertake all or part of the information management function. In which case the appointing party shall establish a scope of services for that appointment. In doing this, the appointing party shall consider the tasks that the prospective lead appointed party or third par5.1.1 Appoint individuals to undertake the information management function
See the evidence: Information management scope of services
- Define information management roles and delegated responsibilities across project appointments · Action Statement · Verified
- Integrate information management milestones into the Project Execution Plan · Action Statement · Verified
| Document information | | | |---|---|---| | Title | Guidance | Information | | Project | What Project is the Plan for? | Project Name | | Title | What is the title of this document? | Information Management Plan - Delivery Team | | Quality | Who performed the quality check on this document? | Checked PL / Reviewed PL / Approved PL | | Document File Naming | What is this document's file naming? | InformationManagementPlan-DeliveryTeam.xlsx | | Version | What is this document's current version? |Instruction
See the evidence: Integrate information management milestones into the Project Execution Plan - Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender and procurement documentation - Tender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender evaluation criteria for information management - Information delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Information delivery risk assessment - Establish the project common data environment that every delivery team will use · Action Statement · Suggested – reviewSee the evidence: Establish the project common data environment that every delivery team will use
- Project Execution Plan (PEP) · Information Use · Verified
The Project Coordinator (continued) Responsibilities The Project Coordinator is responsible for the following: - Managing the Project Programme; - Developing the Project Execution Plan; - Approving interim reports and ensuring that any project changes are evaluated and reported; - Ensuring the development of the Definitive Project Brief; - Ensuring that all stakeholders (including end users) are involved with and committed to the project; - Managing project reviews and obtaining approval from th1.4 Managing the Project Programme, Continued, Continued › 3.2 Management Team: Roles and Responsibilities, Continued
See the evidence: Project Execution Plan (PEP)
- Integrate information management milestones into the Project Execution Plan · Action Statement · Verified
- Monitor all security-related provisions · Action Statement · Verified
monitor and enforce all security-related provisions
See the evidence: Monitor all security-related provisions - Project information standard and protocol · Information Use · Verified
| – the appointing party’s exchange information requirements; | | EIR (Exchange Information Requirements) | | – the relevant reference information and shared resources (within the project’s common data environment); | | Supporting information | | – the tender response requirements and evaluation criteria (if applicable); | | Acceptance criteria | | – the project information delivery milestones; | | Evaluation criteria | | – the project’s information standard; | | Acceptance criteria | | – the prInstruction
See the evidence: Project information standard and protocol - Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender and procurement documentation
- Monitor all security-related provisions · Action Statement · Verified
- Specify Common Data Environment workflows and information exchange rules · Action Statement · Verified
The Senior Information Manager (BIM) is responsible for leading and overseeing Information Management on complex, high-value, or high-risk projects, or across multiple concurrent projects. This role ensures that Information Management processes are fully aligned with the CWMF BIM requirement (Irish BIM mandate) and also align with the ISO 19650 series, the Capital Works Management Framework (CWMF), Infrastructure Guidelines, and client asset information requirements. The Senior Information Manag
See the evidence: Specify Common Data Environment workflows and information exchange rules - Project information standard and protocol · Information Use · Verified
| – the appointing party’s exchange information requirements; | | EIR (Exchange Information Requirements) | | – the relevant reference information and shared resources (within the project’s common data environment); | | Supporting information | | – the tender response requirements and evaluation criteria (if applicable); | | Acceptance criteria | | – the project information delivery milestones; | | Evaluation criteria | | – the project’s information standard; | | Acceptance criteria | | – the prInstruction
See the evidence: Project information standard and protocol
- Specify Common Data Environment workflows and information exchange rules · Action Statement · Verified
- Create clear rules for naming, sharing, and checking information · Action Statement · Verified
Create clear rules for naming, sharing, and checking information,
See the evidence: Create clear rules for naming, sharing, and checking information - Project information standard and protocol · Information Use · Verified
| – the appointing party’s exchange information requirements; | | EIR (Exchange Information Requirements) | | – the relevant reference information and shared resources (within the project’s common data environment); | | Supporting information | | – the tender response requirements and evaluation criteria (if applicable); | | Acceptance criteria | | – the project information delivery milestones; | | Evaluation criteria | | – the project’s information standard; | | Acceptance criteria | | – the prInstruction
See the evidence: Project information standard and protocol
- Create clear rules for naming, sharing, and checking information · Action Statement · Verified
Stage 4: Issue the design team tender with the EIR
Public Sector Project Coordinator
Put the exchange information requirements and the information management evaluation criteria into the design team invitation to tender.
Responsible: Public Sector Project Coordinator
Who does what at this stage
Public Sector Project Coordinator
The role
Carries out stage 4
Issue the design team tender with the EIR
- Sends 3: Invitation to tender with the EIR, shared in the CDE to Lead appointed party (design team) (issue)
- Receives 2: Draft EIR and evaluation criteria for each appointment from Information Manager (submit)
Information Manager
A function the scenario names
- Sends 2: Draft EIR and evaluation criteria for each appointment to Public Sector Project Coordinator (submit)
Lead appointed party (design team)
ISO 19650 party
- Receives 3: Invitation to tender with the EIR, shared in the CDE from Public Sector Project Coordinator (issue)
Contractor
ISO 19650 party
No part in this stage.
Sanctioning Authority
A governance body in the framework
No part in this stage.
No part in this stage: Contractor, Sanctioning Authority.
Hand-offs at this stage
2Draft EIR and evaluation criteria for each appointment
- From
- Information Manager
- To
- Public Sector Project Coordinator
- Hand-off
- Submit
3Invitation to tender with the EIR, shared in the CDE
- From
- Public Sector Project Coordinator
- To
- Lead appointed party (design team)
- Hand-off
- Issue
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 2 | Information Manager | Public Sector Project Coordinator | Submit | Draft EIR and evaluation criteria for each appointment |
| 3 | Public Sector Project Coordinator | Lead appointed party (design team) | Issue | Invitation to tender with the EIR, shared in the CDE |
Checklist
0 of 7 ticked- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Incorporate the BIM Mandate's information requirements in project management and procurement - Incorporate Exchange Information Requirements into public tender documentation · Action Statement · Verified
- Act as the lead project information manager for assigned projects, ensuring compliance with ISO 19650 and CWMF/ Infrastructure Guidelines deliverables. - Develop and implement the project's Information Management Plan (IM Plan), including processes for information production, validation, and exchange. - Ensure compliance with exchange information requirements (EIR), asset information requirements (AIR), and project information requirements (PIR). - Manage the CDE, overseeing information workfl
See the evidence: Incorporate Exchange Information Requirements into public tender documentation - Capital Works Management Framework (CWMF) guidance and templates · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Capital Works Management Framework (CWMF) guidance and templates - Exchange Information Requirements (EIR) · Information Use · Verified
- Act as the lead project information manager for assigned projects, ensuring compliance with ISO 19650 and CWMF/ Infrastructure Guidelines deliverables. - Develop and implement the project's Information Management Plan (IM Plan), including processes for information production, validation, and exchange. - Ensure compliance with exchange information requirements (EIR), asset information requirements (AIR), and project information requirements (PIR). - Manage the CDE, overseeing information workfl
See the evidence: Exchange Information Requirements (EIR)
- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
- Incorporate Exchange Information Requirements into procurement tender documentation · Action Statement · Verified
| – the appointing party’s exchange information requirements; | | EIR (Exchange Information Requirements) | | – the relevant reference information and shared resources (within the project’s common data environment); | | Supporting information | | – the tender response requirements and evaluation criteria (if applicable); | | Acceptance criteria | | – the project information delivery milestones; | | Evaluation criteria | | – the project’s information standard; | | Acceptance criteria | | – the prInstruction
See the evidence: Incorporate Exchange Information Requirements into procurement tender documentation - Tender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender evaluation criteria for information management - Pre-appointment BIM Execution Plan (BEP) · Information Use · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Pre-appointment BIM Execution Plan (BEP) - Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies · Action Statement · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies
- Incorporate Exchange Information Requirements into procurement tender documentation · Action Statement · Verified
- Assess the tasks that the prospective lead appointed party or third party will be responsible for · Action Statement · Verified
The prospective lead appointed party shall nominate individuals from within its organization to undertake the information management function on behalf of its delivery team. Alternatively, the prospective lead appointed party can appoint a prospective appointed party or a third party to undertake all or part of the information management function. In which case the prospective lead appointed party shall establish a scope of services for that appointment. In doing this, the prospective lead appoi5.3.1 Nominate individuals to undertake the information management function
See the evidence: Assess the tasks that the prospective lead appointed party or third party will be responsible for - Specify information management scopes of service for lead appointed parties · Action Statement · Verified
The appointing party shall nominate individuals from within its organization to undertake the information management function. Alternatively, the appointing party can appoint a prospective lead appointed party or a third party to undertake all or part of the information management function. In which case the appointing party shall establish a scope of services for that appointment. In doing this, the appointing party shall consider the tasks that the prospective lead appointed party or third par5.1.1 Appoint individuals to undertake the information management function
See the evidence: Specify information management scopes of service for lead appointed parties - Information management scope of services · Information Use · Verified
The appointing party shall nominate individuals from within its organization to undertake the information management function. Alternatively, the appointing party can appoint a prospective lead appointed party or a third party to undertake all or part of the information management function. In which case the appointing party shall establish a scope of services for that appointment. In doing this, the appointing party shall consider the tasks that the prospective lead appointed party or third par5.1.1 Appoint individuals to undertake the information management function
See the evidence: Information management scope of services - Assess tenderers' information management competence and BIM capability · Action Statement · Verified
The prospective lead appointed party shall have regard to the effective management of information throughout the appointment by nominating individuals from within its own organization to undertake the information management function on behalf of the lead appointed party. Alternatively, the prospective lead appointed party can appoint a prospective appointed party or third party to undertake all or part of the information management function, in which case, the lead appointed party shall establis5.3 Information management process – Tender response › 5.3.1 Nominate individuals to undertake the information management function
See the evidence: Assess tenderers' information management competence and BIM capability
- Assess the tasks that the prospective lead appointed party or third party will be responsible for · Action Statement · Verified
- Incorporate Exchange Information Requirements into public tender documentation · Action Statement · Verified
- Act as the lead project information manager for assigned projects, ensuring compliance with ISO 19650 and CWMF/ Infrastructure Guidelines deliverables. - Develop and implement the project's Information Management Plan (IM Plan), including processes for information production, validation, and exchange. - Ensure compliance with exchange information requirements (EIR), asset information requirements (AIR), and project information requirements (PIR). - Manage the CDE, overseeing information workfl
See the evidence: Incorporate Exchange Information Requirements into public tender documentation - Include Information Management / BIM requirements in your tenders and contracts · Action Statement · Verified
Include Information Management / BIM requirements in your tenders and contracts.
See the evidence: Include Information Management / BIM requirements in your tenders and contracts - Incorporate Exchange Information Requirements into procurement tender documentation · Action Statement · Verified
| – the appointing party’s exchange information requirements; | | EIR (Exchange Information Requirements) | | – the relevant reference information and shared resources (within the project’s common data environment); | | Supporting information | | – the tender response requirements and evaluation criteria (if applicable); | | Acceptance criteria | | – the project information delivery milestones; | | Evaluation criteria | | – the project’s information standard; | | Acceptance criteria | | – the prInstruction
See the evidence: Incorporate Exchange Information Requirements into procurement tender documentation - Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender and procurement documentation
- Incorporate Exchange Information Requirements into public tender documentation · Action Statement · Verified
- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Incorporate the BIM Mandate's information requirements in project management and procurement - Include Information Management / BIM requirements in your tenders and contracts · Action Statement · Verified
Include Information Management / BIM requirements in your tenders and contracts.
See the evidence: Include Information Management / BIM requirements in your tenders and contracts - Specify Information Management / BIM requirements in your tenders and contracts · Action Statement · Verified
Include Information Management / BIM requirements in your tenders and contracts.
See the evidence: Specify Information Management / BIM requirements in your tenders and contracts - Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender and procurement documentation
- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
- Pre-appointment BIM Execution Plan (BEP) · Information Use · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Pre-appointment BIM Execution Plan (BEP) - Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies · Action Statement · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies - Assess the tasks that the prospective lead appointed party or third party will be responsible for · Action Statement · Verified
The prospective lead appointed party shall nominate individuals from within its organization to undertake the information management function on behalf of its delivery team. Alternatively, the prospective lead appointed party can appoint a prospective appointed party or a third party to undertake all or part of the information management function. In which case the prospective lead appointed party shall establish a scope of services for that appointment. In doing this, the prospective lead appoi5.3.1 Nominate individuals to undertake the information management function
See the evidence: Assess the tasks that the prospective lead appointed party or third party will be responsible for - Tender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender evaluation criteria for information management
- Pre-appointment BIM Execution Plan (BEP) · Information Use · Verified
- Assess the tasks that the prospective lead appointed party or third party will be responsible for · Action Statement · Verified
The prospective lead appointed party shall nominate individuals from within its organization to undertake the information management function on behalf of its delivery team. Alternatively, the prospective lead appointed party can appoint a prospective appointed party or a third party to undertake all or part of the information management function. In which case the prospective lead appointed party shall establish a scope of services for that appointment. In doing this, the prospective lead appoi5.3.1 Nominate individuals to undertake the information management function
See the evidence: Assess the tasks that the prospective lead appointed party or third party will be responsible for - Information management scope of services · Information Use · Verified
The appointing party shall nominate individuals from within its organization to undertake the information management function. Alternatively, the appointing party can appoint a prospective lead appointed party or a third party to undertake all or part of the information management function. In which case the appointing party shall establish a scope of services for that appointment. In doing this, the appointing party shall consider the tasks that the prospective lead appointed party or third par5.1.1 Appoint individuals to undertake the information management function
See the evidence: Information management scope of services - Assess tenderers' information management competence and BIM capability · Action Statement · Verified
The prospective lead appointed party shall have regard to the effective management of information throughout the appointment by nominating individuals from within its own organization to undertake the information management function on behalf of the lead appointed party. Alternatively, the prospective lead appointed party can appoint a prospective appointed party or third party to undertake all or part of the information management function, in which case, the lead appointed party shall establis5.3 Information management process – Tender response › 5.3.1 Nominate individuals to undertake the information management function
See the evidence: Assess tenderers' information management competence and BIM capability
- Assess the tasks that the prospective lead appointed party or third party will be responsible for · Action Statement · Verified
Stage 5: Submit the tender response and pre-appointment BEP
Lead appointed party (design team)
Tendering design teams return a pre-appointment BIM execution plan, a capability and capacity assessment and a mobilisation plan.
Responsible: Lead appointed party (design team)
Who does what at this stage
Public Sector Project Coordinator
The role
- Receives 4: Pre-appointment BEP, capability and mobilisation plan from Lead appointed party (design team) (submit)
Information Manager
A function the scenario names
No part in this stage.
Lead appointed party (design team)
ISO 19650 party
Carries out stage 5
Submit the tender response and pre-appointment BEP
- Sends 4: Pre-appointment BEP, capability and mobilisation plan to Public Sector Project Coordinator (submit)
Contractor
ISO 19650 party
No part in this stage.
Sanctioning Authority
A governance body in the framework
No part in this stage.
No part in this stage: Information Manager, Contractor, Sanctioning Authority.
Hand-offs at this stage
4Pre-appointment BEP, capability and mobilisation plan
- From
- Lead appointed party (design team)
- To
- Public Sector Project Coordinator
- Hand-off
- Submit
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 4 | Lead appointed party (design team) | Public Sector Project Coordinator | Submit | Pre-appointment BEP, capability and mobilisation plan |
Checklist
0 of 6 ticked- Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies · Action Statement · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies - Pre-appointment BIM Execution Plan (BEP) · Information Use · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Pre-appointment BIM Execution Plan (BEP) - Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender and procurement documentation - Tender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender evaluation criteria for information management - Information delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Information delivery risk assessment - Establish the project common data environment that every delivery team will use · Action Statement · Suggested – reviewSee the evidence: Establish the project common data environment that every delivery team will use
- Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies · Action Statement · Verified
- Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies · Action Statement · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies - Delivery team capability and capacity assessment · Information Use · Verified
The Project Coordinator (continued) Responsibilities The Project Coordinator is responsible for the following: - Managing the Project Programme; - Developing the Project Execution Plan; - Approving interim reports and ensuring that any project changes are evaluated and reported; - Ensuring the development of the Definitive Project Brief; - Ensuring that all stakeholders (including end users) are involved with and committed to the project; - Managing project reviews and obtaining approval from th1.4 Managing the Project Programme, Continued, Continued › 3.2 Management Team: Roles and Responsibilities, Continued
See the evidence: Delivery team capability and capacity assessment - Pre-appointment BIM Execution Plan (BEP) · Information Use · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Pre-appointment BIM Execution Plan (BEP) - Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender and procurement documentation - Tender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender evaluation criteria for information management - Information delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Information delivery risk assessment
- Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies · Action Statement · Verified
- Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies · Action Statement · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies - Pre-appointment BIM Execution Plan (BEP) · Information Use · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Pre-appointment BIM Execution Plan (BEP) - Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender and procurement documentation - Tender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender evaluation criteria for information management - Information delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Information delivery risk assessment - Establish the project common data environment that every delivery team will use · Action Statement · Suggested – reviewSee the evidence: Establish the project common data environment that every delivery team will use
- Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies · Action Statement · Verified
- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Incorporate the BIM Mandate's information requirements in project management and procurement - Exchange Information Requirements (EIR) · Information Use · Verified
- Act as the lead project information manager for assigned projects, ensuring compliance with ISO 19650 and CWMF/ Infrastructure Guidelines deliverables. - Develop and implement the project's Information Management Plan (IM Plan), including processes for information production, validation, and exchange. - Ensure compliance with exchange information requirements (EIR), asset information requirements (AIR), and project information requirements (PIR). - Manage the CDE, overseeing information workfl
See the evidence: Exchange Information Requirements (EIR) - Pre-appointment BIM Execution Plan (BEP) · Information Use · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Pre-appointment BIM Execution Plan (BEP) - Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies · Action Statement · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies
- Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
- Evaluate the adequacy of tenderers' pre-appointment BIM Execution Plans against the Exchange Information Requirements · Action Statement · Suggested – reviewSee the evidence: Evaluate the adequacy of tenderers' pre-appointment BIM Execution Plans against the Exchange Information Requirements
- Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies · Action Statement · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies - Tender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the evidence: Tender evaluation criteria for information management - Pre-appointment BIM Execution Plan (BEP) · Information Use · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Pre-appointment BIM Execution Plan (BEP)
- Evaluate the adequacy of tenderers' pre-appointment BIM Execution Plans against the Exchange Information Requirements · Action Statement · Suggested – reviewSee the evidence: Evaluate the adequacy of tenderers' pre-appointment BIM Execution Plans against the Exchange Information Requirements
- Pre-appointment BIM Execution Plan (BEP) · Information Use · Verified
As a minimum for the tender response Lead Appointed Party shall include deliverables outlined in Figure 5.1. As part of this process, the Appointing Party shall consider the following elements within each tender response: - The content and adequacy of the pre-appointment BIM Execution Plan (BEP) submitted by the Lead Appointed Party - The competency and experience of the individuals proposed to undertake the information management function on behalf of the delivery team - The Lead Appointed Part4. Information Exchange › 5.2 Tender Response and Evaluation Criteria
See the evidence: Pre-appointment BIM Execution Plan (BEP)
Stage 6: Evaluate tenders and appoint the delivery teams
Public Sector Project Coordinator
Score the information responses, report to the Sanctioning Authority at each Project Review, and appoint a design team and later a contractor whose BIM execution plans meet the EIR.
Responsible: Public Sector Project Coordinator
Who does what at this stage
Public Sector Project Coordinator
The role
Carries out stage 6
Evaluate tenders and appoint the delivery teams
- Sends 6: Project Review report with the information arrangements to Sanctioning Authority (submit)
- Receives 5: Scores for the information responses from Information Manager (review)
- Receives 7: Gate approval to proceed from Sanctioning Authority (approve)
- Receives 8: Contractor pre-appointment BEP and mobilisation plan from Contractor (submit)
Information Manager
A function the scenario names
- Sends 5: Scores for the information responses to Public Sector Project Coordinator (review)
Lead appointed party (design team)
ISO 19650 party
No part in this stage.
Contractor
ISO 19650 party
- Sends 8: Contractor pre-appointment BEP and mobilisation plan to Public Sector Project Coordinator (submit)
Sanctioning Authority
A governance body in the framework
- Sends 7: Gate approval to proceed to Public Sector Project Coordinator (approve)
- Receives 6: Project Review report with the information arrangements from Public Sector Project Coordinator (submit)
No part in this stage: Lead appointed party (design team).
Hand-offs at this stage
5Scores for the information responses
- From
- Information Manager
- To
- Public Sector Project Coordinator
- Hand-off
- Review
6Project Review report with the information arrangements
- From
- Public Sector Project Coordinator
- To
- Sanctioning Authority
- Hand-off
- Submit
7Gate approval to proceed
- From
- Sanctioning Authority
- To
- Public Sector Project Coordinator
- Hand-off
- Approve
8Contractor pre-appointment BEP and mobilisation plan
- From
- Contractor
- To
- Public Sector Project Coordinator
- Hand-off
- Submit
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 5 | Information Manager | Public Sector Project Coordinator | Review | Scores for the information responses |
| 6 | Public Sector Project Coordinator | Sanctioning Authority | Submit | Project Review report with the information arrangements |
| 7 | Sanctioning Authority | Public Sector Project Coordinator | Approve | Gate approval to proceed |
| 8 | Contractor | Public Sector Project Coordinator | Submit | Contractor pre-appointment BEP and mobilisation plan |
Stage 7: Submit the information model at each stage
Lead appointed party (design team)
The lead appointed party authorises its information model and submits it for acceptance at each CWMF stage and at handover.
Responsible: Lead appointed party (design team)
Who does what at this stage
Public Sector Project Coordinator
The role
- Receives 9: Information model submitted for acceptance from Lead appointed party (design team) (submit)
Information Manager
A function the scenario names
No part in this stage.
Lead appointed party (design team)
ISO 19650 party
Carries out stage 7
Submit the information model at each stage
- Sends 9: Information model submitted for acceptance to Public Sector Project Coordinator (submit)
Contractor
ISO 19650 party
No part in this stage.
Sanctioning Authority
A governance body in the framework
No part in this stage.
No part in this stage: Information Manager, Contractor, Sanctioning Authority.
Hand-offs at this stage
9Information model submitted for acceptance
- From
- Lead appointed party (design team)
- To
- Public Sector Project Coordinator
- Hand-off
- Submit
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 9 | Lead appointed party (design team) | Public Sector Project Coordinator | Submit | Information model submitted for acceptance |
Stage 8: Accept or reject the information at each review and at handover
Public Sector Project Coordinator
Accept the whole information model or reject it for amendment, record the decision in each Project Review, and accept the handover information against the asset information requirements.
Responsible: Public Sector Project Coordinator
Who does what at this stage
Public Sector Project Coordinator
The role
Carries out stage 8
Accept or reject the information at each review and at handover
- Sends 11: Rejected: amend and resubmit to Lead appointed party (design team) (reject)
- Sends 13: Information status at each Project Review to Sanctioning Authority (inform)
- Receives 10: Acceptance recommendation against the EIR from Information Manager (review)
- Receives 12: Handover information and asset data from Contractor (submit)
Information Manager
A function the scenario names
- Sends 10: Acceptance recommendation against the EIR to Public Sector Project Coordinator (review)
Lead appointed party (design team)
ISO 19650 party
- Receives 11: Rejected: amend and resubmit from Public Sector Project Coordinator (reject)
Contractor
ISO 19650 party
- Sends 12: Handover information and asset data to Public Sector Project Coordinator (submit)
Sanctioning Authority
A governance body in the framework
- Receives 13: Information status at each Project Review from Public Sector Project Coordinator (inform)
Hand-offs at this stage
10Acceptance recommendation against the EIR
- From
- Information Manager
- To
- Public Sector Project Coordinator
- Hand-off
- Review
11Rejected: amend and resubmit
- From
- Public Sector Project Coordinator
- To
- Lead appointed party (design team)
- Hand-off
- Reject, returns to stage 7: Submit the information model at each stage
12Handover information and asset data
- From
- Contractor
- To
- Public Sector Project Coordinator
- Hand-off
- Submit
13Information status at each Project Review
- From
- Public Sector Project Coordinator
- To
- Sanctioning Authority
- Hand-off
- Inform
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 10 | Information Manager | Public Sector Project Coordinator | Review | Acceptance recommendation against the EIR |
| 11 | Public Sector Project Coordinator | Lead appointed party (design team) | RejectReturns to stage 7: Submit the information model at each stage | Rejected: amend and resubmit |
| 12 | Contractor | Public Sector Project Coordinator | Submit | Handover information and asset data |
| 13 | Public Sector Project Coordinator | Sanctioning Authority | Inform | Information status at each Project Review |
Evidence for the flow
- E1
Definitive Project Brief · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entry - E2
Facilitate information requirements workshops with project stakeholders · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entry - E3
Establish the Project Information Requirements for key project decision points · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the full evidence entry - E4
Review prospective appointed parties · Action Statement · Verified
review of prospective appointed parties in relation to information management
See the full evidence entry - E5
Align information management processes with the Infrastructure Guidelines and CWMF · Action Statement · Verified
The Senior Information Manager (BIM) is responsible for leading and overseeing Information Management on complex, high-value, or high-risk projects, or across multiple concurrent projects. This role ensures that Information Management processes are fully aligned with the CWMF BIM requirement (Irish BIM mandate) and also align with the ISO 19650 series, the Capital Works Management Framework (CWMF), Infrastructure Guidelines, and client asset information requirements. The Senior Information Manag
See the full evidence entry - E6
Incorporate the BIM Mandate's information requirements in project management and procurement · Action Statement · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the full evidence entry - E7
Tender and procurement documentation · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entry - E8
Tender evaluation criteria for information management · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entry - E9
Information delivery risk assessment · Information Use · Verified
**Table 1 – Scope of documentation covered in this guidance according to EN ISO 19650-2:2018 clause reference** | | Invitation to tender EIR | Tender response pre-appointment BEP | Appointment BEP | | --- | --- | --- | --- | | In scope | 5.2.1 Appointing party’s exchange information requirements a) information requirement b) level of Information Need c) acceptance Criteria d) supporting Information e) information delivery dates | 5.3.2 Delivery team’s (pre-appointment) BIM execution plan a) info1 Scope
See the full evidence entry - E10
Establish the project common data environment that every delivery team will use · Action Statement · Suggested – review
See the full evidence entry
Need this flow in your own tooling? Take an editable copy. It is a one way extract, so edits will not sync back to this report.
Download editable diagramKey actions
Open an Action Statement in the Record using its link icon. Each opens in a new tab.
1 headline and 49 detailed Action Statements are recorded. 6 key detailed actions are shown here, with accepted actions first. Read all Action Statements in the Full Scenario Record (opens in a new tab)
What this role works with
Information Uses recorded for this scenario. Review their suitability for the intended organisation and project.
- 1Delivery team capability and capacity assessment
- 2Definitive Project Brief
- 3Tender evaluation criteria for information management
- 4Asset Information Requirements (AIR)
- 5Information management scope of services
- 6Tender and procurement documentation
- 7Project Information Requirements (PIR)
- 8Information quality assurance and validation reports
- 9Project Execution Plan (PEP)
- 10Capital Works Management Framework (CWMF) guidance and templates
- 11Exchange Information Requirements (EIR)
- 12Pre-appointment BIM Execution Plan (BEP)
- 13Project information standard and protocol
- 14Information delivery risk assessment
- 15Infrastructure Guidelines
How the scenario unfolds
8 stages · 1 decision with 4 optionsOpen a stage to see its activities and decisions. Guidance links open the matching section of the Record in a new tab.
Confirm that the €14 million school project falls under the CWMF BIM requirements for both the design team and contractor appointments, and record it in the Project Execution Plan.
Proposed responsibility: Public Sector Project Coordinator
Who will perform the client information management function?
An in-house nominee.
- Nominate an in-house information manager. Name a member of staff with the competence and time to perform the client information management function, with a written scope and delegated authority.
Rejoin at Set the project and asset information requirements in the Record (opens in a new tab).
An independent third-party consultant.
- Appoint an independent information management consultant. Appoint a consultant under its own COE1 appointment, before the design team tender, so the EIR and CDE are ready to issue.
Rejoin at Set the project and asset information requirements in the Record (opens in a new tab).
Delegated to the lead appointed party.
- Assign client-side tasks to the design team lead. Write client-side information tasks into the design team scope, with different individuals for client-side and delivery-side work, and keep acceptance yourself.
Rejoin at Set the project and asset information requirements in the Record (opens in a new tab).
Hybrid: in-house owner with external support.
- Name an in-house owner and buy in defined support. Name an accountable in-house owner and appoint external support for defined tasks, building in-house capability for later projects.
Rejoin at Set the project and asset information requirements in the Record (opens in a new tab).
Turn each key decision point into the questions you need answered, and capture what the school will need to operate and maintain the building.
Proposed responsibility: Public Sector Project Coordinator
Read practical guidance for Set the project and asset information requirements (opens in a new tab)
Approve the information standard, production methods, protocol and common data environment arrangements that every appointment will follow.
Proposed responsibility: Public Sector Project Coordinator
Put the exchange information requirements and the information management evaluation criteria into the design team invitation to tender.
Proposed responsibility: Public Sector Project Coordinator
Read practical guidance for Issue the design team tender with the EIR (opens in a new tab)
Tendering design teams return a pre-appointment BIM execution plan, a capability and capacity assessment and a mobilisation plan.
Proposed responsibility: Lead appointed party (design team)
Read practical guidance for Submit the tender response and pre-appointment BEP (opens in a new tab)
Score the information responses, report to the Sanctioning Authority at each Project Review, and appoint a design team and later a contractor whose BIM execution plans meet the EIR.
Proposed responsibility: Public Sector Project Coordinator
Read practical guidance for Evaluate tenders and appoint the delivery teams (opens in a new tab)
The lead appointed party authorises its information model and submits it for acceptance at each CWMF stage and at handover.
Proposed responsibility: Lead appointed party (design team)
Read practical guidance for Submit the information model at each stage (opens in a new tab)
Accept the whole information model or reject it for amendment, record the decision in each Project Review, and accept the handover information against the asset information requirements.
Proposed responsibility: Public Sector Project Coordinator
Does the mandate apply?
Ireland – CWMF / Public Works. Applies
As the appointing party (client) on a public works project, you carry the CWMF BIM requirements into the appointments you make. The milestones in force at the 22/10/2026 commencement cover the appointments of: design team (lead appointed / appointed parties), over €5m from 01/07/2026; contractors & supply chain, over €10m from 01/01/2026. Require them in those appointments.
Source: CWMF – Public Sector BIM Adoption Timeline. https://cwmf.gov.ie/en/resources/bim/public-sector-bim-adoption-timeline/
Build Digital materials
The material selection and source metadata recorded for this issue. Proposed uses explain how each material supports the workflow; source availability may change.
Supporting materials
Form for assessing the applicability of Irish BIM mandate requirements to a project.
Tool · XLSX
Assess whether public projects trigger mandatory BIM adoption timelines and establish compliance milestones.
Directly supports the Project Coordinator in verifying that the €14M post-primary school extension falls under the Irish BIM Mandate.
BD-MAT-3125 · Source revision 7cae75b1e5db6ccc654b62456a86657615f9e6d8cf4b003876e6cfb8a6452ef9
Editable appointing-party workbook covering requirements, responsibilities, mobilisation and delivery planning.
Plan · XLSX
Structure client-side appointing party requirements, PIR, AIR, and delivery planning workbooks.
Provides practical templates for the coordinator to develop the project and asset information requirements without starting from scratch.
BD-MAT-3137 · Source revision bf6f773aa1546f8dc146352cf986ba3190fe68c329532322a54e51f1466c5385
- Define Project Information Requirements aligned with the Capital Works Management Framework
- Confirm the Asset Information Requirements that the exchange information requirements must deliver at handover
- Evaluate the tenderers' proposed information delivery strategy
- Incorporate Exchange Information Requirements into public tender documentation
- Incorporate Exchange Information Requirements into procurement tender documentation
This project information standard provides spreadsheet templates and guidance for naming project information in accordance with the Irish National Annex to ISO 19650-2. The support includes the core file-naming workbook, a hyperlink checker, a presentation and a demonstration.
Standard · XLSX
Implement standard file naming conventions aligned with the Irish National Annex to ISO 19650-2.
Provides the required spreadsheet templates and hyperlink checker to specify and verify project naming rules.
Included resources
- Project Information Standard – File Naming · primary · XLSX
BD-MAT-3093 · Source revision f3c82554ee73f2db7a730a64ee511aa2d002510d36418243848f00bee156214a
This support presents the CWMF-to-ISO 19650-2 process workflows, including the Stage (i) feasibility study and preliminary report workflow. It is published as a single PDF support for information-management activities across appointing and appointed parties.
Workflow · PDF
Align ISO 19650-2 information management stages with standard CWMF project workflows.
Directly illustrates how client-side decision points and project reviews map across CWMF stages and ISO 19650 requirements.
Included resources
- Process Workflows CWMF to ISO 19650-2 · primary · PDF
BD-MAT-3134 · Source revision 099ea73d72c1bff960041a4c46f4926277c1ebf1c4af142aefa52b661fedde73
This delivery-team information management plan provides tenderers with a structured set of templates for responding to a project tender in line with ISO 19650. It covers the delivery team’s information-management function, delivery strategy objectives, federation approach, responsibilities, acceptance criteria, capability, mobilisation and risk planning.
Plan · XLSX
Provide tenderers' response structures and benchmark criteria for pre-appointment BIM Execution Plans.
Assists the coordinator in defining tender return requirements and evaluating tenderers' BEP submissions and capability.
Included resources
- Information Management Plan – Delivery Team · primary · XLSX
BD-MAT-3121 · Source revision db789419d913153580cb910c037258fcbf872dafd37dcea0d40bca035b865374
- Assess tenderers' information management competence and BIM capability
- Evaluate the adequacy of tenderers' pre-appointment BIM Execution Plans against the Exchange Information Requirements
- Evaluate tenderers' pre-appointment BIM Execution Plans and digital competencies
- Evaluate tenderers' capability and capacity assessments and information delivery risks before appointing the delivery team
This report defines Information Manager (BIM) role profiles for the Irish built-environment sector. It supports the development of the digital capability needed for more transparent, consistent and long-term infrastructure delivery.
Report · PDF
Benchmark information manager responsibilities, scopes of service, and capability requirements in the Irish built environment.
Provides the public coordinator with standard role profiles to evaluate and select between internal nomination, third-party appointment, or delegation.
Included resources
- Information Manager (BIM) Role Profiles · primary · PDF
BD-MAT-3714 · Source revision 70de02c1fbe66594f4c0ef99a9ce4575d4aa8784220ef8cfda9680c0d25725c6
- Define information management roles and delegated responsibilities across project appointments
- Align Information Managers with CWMF BIM requirements
- Employ suitably graded and competent personnel
- Select individuals whose qualifications reflect structured learning outcomes aligned with ISO 19650 implementation, OpenBIM principles and asset lifecycle Information Management
- Nominate internal individuals or appoint third-party support to undertake the information management function
- Define the scope of services for the individuals or third party undertaking the appointing party's information management function
- Select individuals to undertake the information management function
- Define the specific function of information facilitation or information process management
- Identify types of information management functions
- Allocate information management functions across internal staff or external appointments
This technology evaluation method provides a structured and transparent approach for assessing digital tools that support Information Management and Building Information Modelling (BIM). It establishes consistent criteria for evaluating functionality, interoperability, usability, compliance with standards such as ISO 19650, and alignment with organisational needs. The method supports objective comparison, informed decision-making, and proportionate investment, ensuring that technology acts as an enabler of defined processes rather than a driver in itself. Overall, it helps organisations select and implement technology solutions that are fit for purpose, scalable, and supportive of long-term Information Management / BIM adoption and continuous improvement.
Protocol · XLSX
Evaluate digital tools and Common Data Environment platforms against objective functional criteria.
Supports the coordinator in reviewing client-side or delivery-team Common Data Environments for standards compliance and security readiness.
Included resources
- BIM Technology Evaluation Methodology · primary · XLSX
BD-MAT-3881 · Source revision 3e4ee37a5210f4ea5dcb4a103473d99828b14ea1b12ac4c21a1f56bc244ff410