Information Manager (BIM)
Establishing, implementing and overseeing information management processes within a public client organisation and across its capital projects
Information Manager (BIM): establishing information management for a public client
The scenario
The Information Manager (BIM) works for an Education and Training Board, a public client acting as the in Ireland under the CWMF. The ETB is delivering several projects under the BIM Mandate, but its departments have varying BIM experience, inconsistent information requirements and no standard approach. Information handed over from consultant-managed common data environments is not consistently structured for future use. Their task is to build a consistent, proportionate approach to that works across projects and departments, starting with a €14 million post-primary school extension and refurbishment. By mid 2027, requirements, standards and assurance should be in place, Project Coordinators should apply them unaided, and the ETB should retain usable information after completion.
You can give your ETB a consistent, proportionate approach to that works across every project and department, starting with the €14 million post-primary school, so that information delivered by the design team and contractor is retained and usable long after completion.
Activity flow diagram
Choose Vertical to follow the flow from top to bottom on a narrow screen.
Scroll sideways to follow the flow. With the diagram focused, use the Left and Right arrow keys.
- Information Manager (BIM)
- Project Coordinator
- Lead appointed party
- Contractor
- Issue
- Submit
- Reject
- Returns work to amend and resubmit
Explore the flow by stage
6 stages · 1 decision with 2 optionsChoose a stage to see what each party does in it, the hand-offs between them and any decision that follows. A decision's options are listed under it. The hand-off numbers match the numbered arrows on the diagram.
Each stage below shows what each party does in it, the hand-offs between them and any decision that follows. A decision's options are listed under it. The hand-off numbers match the numbered arrows on the diagram. Each stage's checklist is in the Full Scenario Record.
Decision after stage 5Do the delivered federated models and asset datasets meet EIR acceptance criteria?One option applies.
Stage 1: Audit baseline ETB information management maturity
Information Manager (BIM)
Review existing consultant-managed CDE arrangements and documentation across ETB departments to establish baseline information practices under the CWMF BIM Mandate.
Responsible: Information Manager (BIM)
Who does what at this stage
Information Manager (BIM)
The role
Carries out stage 1
Audit baseline ETB information management maturity
Project Coordinator
A function the scenario names
No part in this stage.
Lead appointed party
ISO 19650 party
No part in this stage.
Contractor
ISO 19650 party
No part in this stage.
No part in this stage: Project Coordinator, Lead appointed party, Contractor.
Hand-offs at this stage
No hand-offs at this stage.
Checklist
0 of 8 ticked- Establish the organisation's information management approach · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the organisation's information management approach - Project information protocol · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Project information protocol - Asset Information Model (AIM) · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Asset Information Model (AIM) - Document the organisational information requirements and asset information requirements · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Document the organisational information requirements and asset information requirements - Establish the project common data environment workflow and access permissions · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the project common data environment workflow and access permissions - Organisational Information Requirements (OIR) · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Organisational Information Requirements (OIR)
- Establish the organisation's information management approach · Action Statement · Verified
- Establish the organisation's information management approach · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the organisation's information management approach - Project information protocol · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Project information protocol - Asset Information Model (AIM) · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Asset Information Model (AIM) - Document the organisational information requirements and asset information requirements · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Document the organisational information requirements and asset information requirements - Establish the project common data environment workflow and access permissions · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the project common data environment workflow and access permissions - Project Information Requirements (PIR) · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Project Information Requirements (PIR)
- Establish the organisation's information management approach · Action Statement · Verified
- Project information protocol · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Project information protocol - Asset Information Model (AIM) · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Asset Information Model (AIM) - Establish the organisation's information management approach · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the organisation's information management approach - Document the organisational information requirements and asset information requirements · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Document the organisational information requirements and asset information requirements - Establish the project common data environment workflow and access permissions · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the project common data environment workflow and access permissions
- Project information protocol · Information Use · Verified
- Appoint individuals to undertake the information management function · Action Statement · Verified
#### 5.1.1 Appoint individuals to undertake the information management function The appointing party shall have regard to the effective management of information throughout the project and reflect the long-term asset information management strategy, as described in ISO 19650-1:2018, 5.3, by nominating individuals from within the appointing party's organization to undertake the information management function on behalf of the appointing party. Alternatively, the appointing party can appoint a pro5 Information management process during the delivery phase of assets › 5.1 Information management process – Assessment and need
See the evidence: Appoint individuals to undertake the information management function - Information management function schedule and resourcing records · Information Use · Verified
The information management function response informs the appointing party who (named individual) will be responsible for information management during the project. This will include the lead appointed party and known task team's information manager at pre-appointment. At appointment all task team's information manager should be included. The response shall demonstrate that the proposed individual is competent to perform the function. This also gives the delivery team clarity about the allocation6.2 Information management function
See the evidence: Information management function schedule and resourcing records
- Appoint individuals to undertake the information management function · Action Statement · Verified
- Establish the organisation's information management approach · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the organisation's information management approach - Project information protocol · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Project information protocol - Asset Information Model (AIM) · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Asset Information Model (AIM) - Document the organisational information requirements and asset information requirements · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Document the organisational information requirements and asset information requirements - Establish the project common data environment workflow and access permissions · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the project common data environment workflow and access permissions - Information management function schedule and resourcing records · Information Use · Verified
The information management function response informs the appointing party who (named individual) will be responsible for information management during the project. This will include the lead appointed party and known task team's information manager at pre-appointment. At appointment all task team's information manager should be included. The response shall demonstrate that the proposed individual is competent to perform the function. This also gives the delivery team clarity about the allocation6.2 Information management function
See the evidence: Information management function schedule and resourcing records
- Establish the organisation's information management approach · Action Statement · Verified
- Appoint individuals to undertake the information management function · Action Statement · Verified
#### 5.1.1 Appoint individuals to undertake the information management function The appointing party shall have regard to the effective management of information throughout the project and reflect the long-term asset information management strategy, as described in ISO 19650-1:2018, 5.3, by nominating individuals from within the appointing party's organization to undertake the information management function on behalf of the appointing party. Alternatively, the appointing party can appoint a pro5 Information management process during the delivery phase of assets › 5.1 Information management process – Assessment and need
See the evidence: Appoint individuals to undertake the information management function
- Appoint individuals to undertake the information management function · Action Statement · Verified
- Common Data Environment (CDE) solution and workflow · Information Use · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Common Data Environment (CDE) solution and workflow
- Common Data Environment (CDE) solution and workflow · Information Use · Verified
- Common Data Environment (CDE) solution and workflow · Information Use · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Common Data Environment (CDE) solution and workflow
- Common Data Environment (CDE) solution and workflow · Information Use · Verified
Stage 2: Establish ETB OIR, AIR, and PIR framework
Information Manager (BIM)
Define standard Organisational and Asset Information Requirements alongside Project Information Requirements for the €14m post-primary school refurbishment.
Responsible: Information Manager (BIM)
Who does what at this stage
Information Manager (BIM)
The role
Carries out stage 2
Establish ETB OIR, AIR, and PIR framework
Project Coordinator
A function the scenario names
No part in this stage.
Lead appointed party
ISO 19650 party
No part in this stage.
Contractor
ISO 19650 party
No part in this stage.
No part in this stage: Project Coordinator, Lead appointed party, Contractor.
Hand-offs at this stage
No hand-offs at this stage.
Checklist
0 of 8 ticked- Appoint individuals to undertake the information management function · Action Statement · Verified
#### 5.1.1 Appoint individuals to undertake the information management function The appointing party shall have regard to the effective management of information throughout the project and reflect the long-term asset information management strategy, as described in ISO 19650-1:2018, 5.3, by nominating individuals from within the appointing party's organization to undertake the information management function on behalf of the appointing party. Alternatively, the appointing party can appoint a pro5 Information management process during the delivery phase of assets › 5.1 Information management process – Assessment and need
See the evidence: Appoint individuals to undertake the information management function - Project information protocol · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Project information protocol - Asset Information Model (AIM) · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Asset Information Model (AIM) - Document the organisational information requirements and asset information requirements · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Document the organisational information requirements and asset information requirements - Establish the project common data environment workflow and access permissions · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the project common data environment workflow and access permissions - Information management function schedule and resourcing records · Information Use · Verified
The information management function response informs the appointing party who (named individual) will be responsible for information management during the project. This will include the lead appointed party and known task team's information manager at pre-appointment. At appointment all task team's information manager should be included. The response shall demonstrate that the proposed individual is competent to perform the function. This also gives the delivery team clarity about the allocation6.2 Information management function
See the evidence: Information management function schedule and resourcing records
- Appoint individuals to undertake the information management function · Action Statement · Verified
- Document the organisational information requirements and asset information requirements · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Document the organisational information requirements and asset information requirements - Project information protocol · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Project information protocol - Asset Information Model (AIM) · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Asset Information Model (AIM) - Establish the organisation's information management approach · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the organisation's information management approach - Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Organisational Information Requirements (OIR) · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Organisational Information Requirements (OIR)
- Document the organisational information requirements and asset information requirements · Action Statement · Verified
- Document the organisational information requirements and asset information requirements · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Document the organisational information requirements and asset information requirements - Project information protocol · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Project information protocol - Asset Information Model (AIM) · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Asset Information Model (AIM) - Establish the organisation's information management approach · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the organisation's information management approach - Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Asset Information Requirements (AIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Asset Information Requirements (AIR)
- Document the organisational information requirements and asset information requirements · Action Statement · Verified
- Capture key decision points and project information requirements · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Capture key decision points and project information requirements - Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Project Information Requirements (PIR) · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Project Information Requirements (PIR)
- Capture key decision points and project information requirements · Action Statement · Verified
- Establish the project information standard and production procedures · Action Statement · Verified
The appointing party may have specified the project's information standard. For more information refer to 5.4.2 of this guidance. The prospective lead appointed party has to communicate their response to the requirements. They can accept or reject the use of the appointing party's project's information standard and suggest additions or amendments to them. Information shall be produced in line with the project's information standard to ensure successful exchange with other technologies, using ope6.7 Project's information standard
See the evidence: Establish the project information standard and production procedures - Project information protocol · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Project information protocol - Establish the organisation's information management approach · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the organisation's information management approach - Document the organisational information requirements and asset information requirements · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Document the organisational information requirements and asset information requirements - Establish the project common data environment workflow and access permissions · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the project common data environment workflow and access permissions - Project information standard · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information standard
- Establish the project information standard and production procedures · Action Statement · Verified
- Establish the project information standard and production procedures · Action Statement · Verified
The appointing party may have specified the project's information standard. For more information refer to 5.4.2 of this guidance. The prospective lead appointed party has to communicate their response to the requirements. They can accept or reject the use of the appointing party's project's information standard and suggest additions or amendments to them. Information shall be produced in line with the project's information standard to ensure successful exchange with other technologies, using ope6.7 Project's information standard
See the evidence: Establish the project information standard and production procedures - Project information protocol · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Project information protocol - Establish the organisation's information management approach · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the organisation's information management approach - Document the organisational information requirements and asset information requirements · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Document the organisational information requirements and asset information requirements - Establish the project common data environment workflow and access permissions · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the project common data environment workflow and access permissions - Information production methods and procedures · Information Use · Verified
The lead appointed party shall establish a detailed responsibility matrix, to confirm the information to be produced, when the information is to be exchanged with whom, and which task team is responsible for its production. In doing this, the lead appointed party shall consider: – the information delivery milestones; – the capability and capacity across the delivery team; © ISO 2020 – All rights reserved 15 --- ISO/FDIS 19650-3:2020(E) - the asset information production methods and procedures; -5.3.1 Nominate individuals to undertake the information management function › 5.4 Information management process – Appointment › 5.4.2 Establish the delivery team's detailed responsibility matrix
See the evidence: Information production methods and procedures
- Establish the project information standard and production procedures · Action Statement · Verified
- Establish the organisation's information management approach · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the organisation's information management approach - Project information protocol · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Project information protocol - Asset Information Model (AIM) · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Asset Information Model (AIM) - Document the organisational information requirements and asset information requirements · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Document the organisational information requirements and asset information requirements - Establish the project common data environment workflow and access permissions · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the project common data environment workflow and access permissions - Asset Information Requirements (AIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Asset Information Requirements (AIR)
- Establish the organisation's information management approach · Action Statement · Verified
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Exchange Information Requirements (EIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Exchange Information Requirements (EIR) - Asset Information Requirements (AIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Asset Information Requirements (AIR) - Specify the appointing party's exchange information requirements for each lead appointed party appointment · Action Statement · Suggested – reviewSee the evidence: Specify the appointing party's exchange information requirements for each lead appointed party appointment
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
Stage 3: Embed CWMF EIR into appointment documents
Information Manager (BIM)
Incorporate the Exchange Information Requirements and project information protocol into CWMF procurement documents, enforcing the Irish BIM Mandate milestones for design and works contracts over €5m and €10m.
Responsible: Information Manager (BIM)
Who does what at this stage
Information Manager (BIM)
The role
Carries out stage 3
Embed CWMF EIR into appointment documents
- Sends 1: Exchange Information Requirements and appointment protocol to Project Coordinator (issue)
Project Coordinator
A function the scenario names
- Receives 1: Exchange Information Requirements and appointment protocol from Information Manager (BIM) (issue)
Lead appointed party
ISO 19650 party
No part in this stage.
Contractor
ISO 19650 party
No part in this stage.
No part in this stage: Lead appointed party, Contractor.
Hand-offs at this stage
1Exchange Information Requirements and appointment protocol
- From
- Information Manager (BIM)
- To
- Project Coordinator
- Hand-off
- Issue
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 1 | Information Manager (BIM) | Project Coordinator | Issue | Exchange Information Requirements and appointment protocol |
Checklist
0 of 8 ticked- Capture key decision points and project information requirements · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Capture key decision points and project information requirements - Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Project Information Requirements (PIR) · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Project Information Requirements (PIR)
- Capture key decision points and project information requirements · Action Statement · Verified
- Specify the appointing party's exchange information requirements for each lead appointed party appointment · Action Statement · Suggested – reviewSee the evidence: Specify the appointing party's exchange information requirements for each lead appointed party appointment
- Exchange Information Requirements (EIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Exchange Information Requirements (EIR) - Asset Information Requirements (AIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Asset Information Requirements (AIR) - Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes
- Establish the project information standard and production procedures · Action Statement · Verified
The appointing party may have specified the project's information standard. For more information refer to 5.4.2 of this guidance. The prospective lead appointed party has to communicate their response to the requirements. They can accept or reject the use of the appointing party's project's information standard and suggest additions or amendments to them. Information shall be produced in line with the project's information standard to ensure successful exchange with other technologies, using ope6.7 Project's information standard
See the evidence: Establish the project information standard and production procedures - Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Project information standard · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information standard
- Establish the project information standard and production procedures · Action Statement · Verified
- Capture key decision points and project information requirements · Action Statement · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Capture key decision points and project information requirements - Project Information Requirements (PIR) · Information Use · Verified
| project information requirements | | | | | | |---|---|---|---|---|---| | 5.4 Project information requirements (PIR) | | | | | | | PIR explain the information needed to answer or inform high-level strategic objectives within the appointing party in relation to a particular built asset project. management process. | | | | | | | PIR are identified from both the project management process and the asset | | | | | | | A set of information requirements should be prepared for each of the appointing paInstruction › PIR
See the evidence: Project Information Requirements (PIR) - Exchange Information Requirements (EIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Exchange Information Requirements (EIR)
- Capture key decision points and project information requirements · Action Statement · Verified
- Validate supplier information management capability and execution proposals · Action Statement · Verified
The prospective lead appointed party shall nominate individuals from within its organization to undertake the information management function on behalf of its delivery team. Alternatively, the prospective lead appointed party can appoint a prospective appointed party or a third party to undertake all or part of the information management function. In which case the prospective lead appointed party shall establish a scope of services for that appointment. In doing this, the prospective lead appoi5.3.1 Nominate individuals to undertake the information management function
See the evidence: Validate supplier information management capability and execution proposals - Information management function schedule and resourcing records · Information Use · Verified
The information management function response informs the appointing party who (named individual) will be responsible for information management during the project. This will include the lead appointed party and known task team's information manager at pre-appointment. At appointment all task team's information manager should be included. The response shall demonstrate that the proposed individual is competent to perform the function. This also gives the delivery team clarity about the allocation6.2 Information management function
See the evidence: Information management function schedule and resourcing records
- Validate supplier information management capability and execution proposals · Action Statement · Verified
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Validate supplier information management capability and execution proposals · Action Statement · Verified
The prospective lead appointed party shall nominate individuals from within its organization to undertake the information management function on behalf of its delivery team. Alternatively, the prospective lead appointed party can appoint a prospective appointed party or a third party to undertake all or part of the information management function. In which case the prospective lead appointed party shall establish a scope of services for that appointment. In doing this, the prospective lead appoi5.3.1 Nominate individuals to undertake the information management function
See the evidence: Validate supplier information management capability and execution proposals - Information management function schedule and resourcing records · Information Use · Verified
The information management function response informs the appointing party who (named individual) will be responsible for information management during the project. This will include the lead appointed party and known task team's information manager at pre-appointment. At appointment all task team's information manager should be included. The response shall demonstrate that the proposed individual is competent to perform the function. This also gives the delivery team clarity about the allocation6.2 Information management function
See the evidence: Information management function schedule and resourcing records
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Common Data Environment (CDE) solution and workflow · Information Use · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Common Data Environment (CDE) solution and workflow
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Project information protocol · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Project information protocol
- Project information protocol · Information Use · Verified
Stage 4: Configure client CDE and assess lead BEP
Information Manager (BIM)
Establish the client Common Data Environment workflow with role-based permissions and evaluate the Lead appointed party BIM Execution Plan and Master Information Delivery Plan.
Responsible: Information Manager (BIM)
Who does what at this stage
Information Manager (BIM)
The role
Carries out stage 4
Configure client CDE and assess lead BEP
- Receives 2: BIM Execution Plan and Master Information Delivery Plan from Lead appointed party (submit)
Project Coordinator
A function the scenario names
No part in this stage.
Lead appointed party
ISO 19650 party
- Sends 2: BIM Execution Plan and Master Information Delivery Plan to Information Manager (BIM) (submit)
Contractor
ISO 19650 party
No part in this stage.
No part in this stage: Project Coordinator, Contractor.
Hand-offs at this stage
2BIM Execution Plan and Master Information Delivery Plan
- From
- Lead appointed party
- To
- Information Manager (BIM)
- Hand-off
- Submit
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 2 | Lead appointed party | Information Manager (BIM) | Submit | BIM Execution Plan and Master Information Delivery Plan |
Checklist
0 of 7 ticked- Establish the project common data environment workflow and access permissions · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the project common data environment workflow and access permissions - Common Data Environment (CDE) solution and workflow · Information Use · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Common Data Environment (CDE) solution and workflow
- Establish the project common data environment workflow and access permissions · Action Statement · Verified
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Establish the project common data environment workflow and access permissions · Action Statement · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Establish the project common data environment workflow and access permissions - Common Data Environment (CDE) solution and workflow · Information Use · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Common Data Environment (CDE) solution and workflow
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Validate supplier information management capability and execution proposals · Action Statement · Verified
The prospective lead appointed party shall nominate individuals from within its organization to undertake the information management function on behalf of its delivery team. Alternatively, the prospective lead appointed party can appoint a prospective appointed party or a third party to undertake all or part of the information management function. In which case the prospective lead appointed party shall establish a scope of services for that appointment. In doing this, the prospective lead appoi5.3.1 Nominate individuals to undertake the information management function
See the evidence: Validate supplier information management capability and execution proposals - Information management function schedule and resourcing records · Information Use · Verified
The information management function response informs the appointing party who (named individual) will be responsible for information management during the project. This will include the lead appointed party and known task team's information manager at pre-appointment. At appointment all task team's information manager should be included. The response shall demonstrate that the proposed individual is competent to perform the function. This also gives the delivery team clarity about the allocation6.2 Information management function
See the evidence: Information management function schedule and resourcing records
- Validate supplier information management capability and execution proposals · Action Statement · Verified
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Validate supplier information management capability and execution proposals · Action Statement · Verified
The prospective lead appointed party shall nominate individuals from within its organization to undertake the information management function on behalf of its delivery team. Alternatively, the prospective lead appointed party can appoint a prospective appointed party or a third party to undertake all or part of the information management function. In which case the prospective lead appointed party shall establish a scope of services for that appointment. In doing this, the prospective lead appoi5.3.1 Nominate individuals to undertake the information management function
See the evidence: Validate supplier information management capability and execution proposals - Project information standard · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information standard - Exchange Information Requirements (EIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Exchange Information Requirements (EIR)
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Master Information Delivery Plan (MIDP) · Information Use · Verified
The lead appointed party shall establish a detailed responsibility matrix, to confirm the information to be produced, when the information is to be exchanged with whom, and which task team is responsible for its production. In doing this, the lead appointed party shall consider: – the information delivery milestones; – the capability and capacity across the delivery team; © ISO 2020 – All rights reserved 15 --- ISO/FDIS 19650-3:2020(E) - the asset information production methods and procedures; -5.3.1 Nominate individuals to undertake the information management function › 5.4 Information management process – Appointment › 5.4.2 Establish the delivery team's detailed responsibility matrix
See the evidence: Master Information Delivery Plan (MIDP) - Information production methods and procedures · Information Use · Verified
The lead appointed party shall establish a detailed responsibility matrix, to confirm the information to be produced, when the information is to be exchanged with whom, and which task team is responsible for its production. In doing this, the lead appointed party shall consider: – the information delivery milestones; – the capability and capacity across the delivery team; © ISO 2020 – All rights reserved 15 --- ISO/FDIS 19650-3:2020(E) - the asset information production methods and procedures; -5.3.1 Nominate individuals to undertake the information management function › 5.4 Information management process – Appointment › 5.4.2 Establish the delivery team's detailed responsibility matrix
See the evidence: Information production methods and procedures - Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes
- Master Information Delivery Plan (MIDP) · Information Use · Verified
- Master Information Delivery Plan (MIDP) · Information Use · Verified
The lead appointed party shall establish a detailed responsibility matrix, to confirm the information to be produced, when the information is to be exchanged with whom, and which task team is responsible for its production. In doing this, the lead appointed party shall consider: – the information delivery milestones; – the capability and capacity across the delivery team; © ISO 2020 – All rights reserved 15 --- ISO/FDIS 19650-3:2020(E) - the asset information production methods and procedures; -5.3.1 Nominate individuals to undertake the information management function › 5.4 Information management process – Appointment › 5.4.2 Establish the delivery team's detailed responsibility matrix
See the evidence: Master Information Delivery Plan (MIDP) - Information production methods and procedures · Information Use · Verified
The lead appointed party shall establish a detailed responsibility matrix, to confirm the information to be produced, when the information is to be exchanged with whom, and which task team is responsible for its production. In doing this, the lead appointed party shall consider: – the information delivery milestones; – the capability and capacity across the delivery team; © ISO 2020 – All rights reserved 15 --- ISO/FDIS 19650-3:2020(E) - the asset information production methods and procedures; -5.3.1 Nominate individuals to undertake the information management function › 5.4 Information management process – Appointment › 5.4.2 Establish the delivery team's detailed responsibility matrix
See the evidence: Information production methods and procedures - Validate supplier information management capability and execution proposals · Action Statement · Verified
The prospective lead appointed party shall nominate individuals from within its organization to undertake the information management function on behalf of its delivery team. Alternatively, the prospective lead appointed party can appoint a prospective appointed party or a third party to undertake all or part of the information management function. In which case the prospective lead appointed party shall establish a scope of services for that appointment. In doing this, the prospective lead appoi5.3.1 Nominate individuals to undertake the information management function
See the evidence: Validate supplier information management capability and execution proposals
- Master Information Delivery Plan (MIDP) · Information Use · Verified
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Exchange Information Requirements (EIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Exchange Information Requirements (EIR)
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
Stage 5: Assure federated models and asset data
Information Manager (BIM)
Audit federated design models and contractor asset information against defined acceptance criteria, classification standards, and naming conventions.
Responsible: Information Manager (BIM)
Who does what at this stage
Information Manager (BIM)
The role
Carries out stage 5
Assure federated models and asset data
Then decides: Do the delivered federated models and asset datasets meet EIR acceptance criteria?
- Receives 3: Federated Information Model and design data containers from Lead appointed party (submit)
- Receives 4: As-built asset information and COBie deliverables from Contractor (submit)
Project Coordinator
A function the scenario names
No part in this stage.
Lead appointed party
ISO 19650 party
- Sends 3: Federated Information Model and design data containers to Information Manager (BIM) (submit)
Contractor
ISO 19650 party
- Sends 4: As-built asset information and COBie deliverables to Information Manager (BIM) (submit)
No part in this stage: Project Coordinator.
Hand-offs at this stage
3Federated Information Model and design data containers
- From
- Lead appointed party
- To
- Information Manager (BIM)
- Hand-off
- Submit
4As-built asset information and COBie deliverables
- From
- Contractor
- To
- Information Manager (BIM)
- Hand-off
- Submit
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 3 | Lead appointed party | Information Manager (BIM) | Submit | Federated Information Model and design data containers |
| 4 | Contractor | Information Manager (BIM) | Submit | As-built asset information and COBie deliverables |
Decision: Do the delivered federated models and asset datasets meet EIR acceptance criteria?
After stage 5: Assure federated models and asset data. One option applies. Marks show how well each option meets a criterion. They are not scores, and they are not added up or ranked.
| Criterion | Option ADeliverables meet all EIR acceptance criteria | Option 5.1Information deliverables require corrective revisions |
|---|---|---|
| EIR and acceptance criteria complianceDoes the delivered information model satisfy all defined acceptance criteria in the appointing party EIR? Evidence: E1 Review the information model against defined acceptance criteria
| +Strong All defined acceptance criteria and levels of information need are fully achieved Evidence: E1 Review the information model against defined acceptance criteria
| –Weak Deliverables fail specific EIR acceptance criteria or level of information need requirements Evidence: E1 Review the information model against defined acceptance criteria
|
| MIDP deliverable completenessAre all required information deliverables listed in the master information delivery plan provided? Evidence: E1 Review the information model against defined acceptance criteria
| +Strong All deliverables scheduled within the master information delivery plan are included Evidence: E1 Review the information model against defined acceptance criteria
| ~Depends Deliverables may be incomplete or misaligned with MIDP schedule milestones Evidence: E1 Review the information model against defined acceptance criteria
|
| Data format and schema conformanceDo the information containers adhere to the agreed exchange schema and data formats? | +Strong Container formats conform strictly to agreed project information standards | ~Depends Data format deviations or schema mismatches may prevent acceptance |
Option A
Deliverables meet all EIR acceptance criteria
Rejoins at stage 6: Transfer verified AIM to post-primary school operations.
- EIR and acceptance criteria compliance
- +StrongAll defined acceptance criteria and levels of information need are fully achieved
Evidence: E1 Review the information model against defined acceptance criteria
Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the full evidence entry
- MIDP deliverable completeness
- +StrongAll deliverables scheduled within the master information delivery plan are included
Evidence: E1 Review the information model against defined acceptance criteria
Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the full evidence entry
- Data format and schema conformance
- +StrongContainer formats conform strictly to agreed project information standards
Consequences
- The appointing party accepts the information model as an authorized deliverable within the common data environment
Evidence: E1 Review the information model against defined acceptance criteria
Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the full evidence entry
- The verified information containers can be progressed towards incorporation into the Asset Information Model
Evidence: E1 Review the information model against defined acceptance criteria
Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the full evidence entry
Option 5.1
Information deliverables require corrective revisions
- Option 5.1: Coordinate correction of non-compliant information containers
Rejoins at stage 6: Transfer verified AIM to post-primary school operations.
- EIR and acceptance criteria compliance
- –WeakDeliverables fail specific EIR acceptance criteria or level of information need requirements
Evidence: E1 Review the information model against defined acceptance criteria
Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the full evidence entry
- MIDP deliverable completeness
- ~DependsDeliverables may be incomplete or misaligned with MIDP schedule milestones
Evidence: E1 Review the information model against defined acceptance criteria
Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the full evidence entry
- Data format and schema conformance
- ~DependsData format deviations or schema mismatches may prevent acceptance
Consequences
- The entire information model is rejected to prevent coordination issues resulting from partial acceptance
Evidence: E1 Review the information model against defined acceptance criteria
Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the full evidence entry
- The lead appointed party is instructed to amend non-compliant information containers and re-submit for review
Evidence: E1 Review the information model against defined acceptance criteria
Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the full evidence entry
Evidence: E1 Review the information model against defined acceptance criteria
Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the full evidence entry
Checklist
0 of 6 ticked- Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the evidence: Review the information model against defined acceptance criteria - Master Information Delivery Plan (MIDP) · Information Use · Verified
The lead appointed party shall establish a detailed responsibility matrix, to confirm the information to be produced, when the information is to be exchanged with whom, and which task team is responsible for its production. In doing this, the lead appointed party shall consider: – the information delivery milestones; – the capability and capacity across the delivery team; © ISO 2020 – All rights reserved 15 --- ISO/FDIS 19650-3:2020(E) - the asset information production methods and procedures; -5.3.1 Nominate individuals to undertake the information management function › 5.4 Information management process – Appointment › 5.4.2 Establish the delivery team's detailed responsibility matrix
See the evidence: Master Information Delivery Plan (MIDP)
- Review the information model against defined acceptance criteria · Action Statement · Verified
- Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the evidence: Review the information model against defined acceptance criteria - Project information standard · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information standard
- Review the information model against defined acceptance criteria · Action Statement · Verified
- Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the evidence: Review the information model against defined acceptance criteria - Exchange Information Requirements (EIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Exchange Information Requirements (EIR)
- Review the information model against defined acceptance criteria · Action Statement · Verified
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Common Data Environment (CDE) solution and workflow · Information Use · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Common Data Environment (CDE) solution and workflow
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Exchange Information Requirements (EIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Exchange Information Requirements (EIR)
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the evidence: Review the information model against defined acceptance criteria - Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes
- Review the information model against defined acceptance criteria · Action Statement · Verified
Option 5.1: Coordinate correction of non-compliant information containers
Information Manager (BIM) · an option of the decision after stage 5: Assure federated models and asset data
Issue corrective notices detailing metadata and geometric defects to the delivery team and verify resubmitted containers against the EIR.
Responsible: Information Manager (BIM)
Who does what at this stage
Information Manager (BIM)
The role
Carries out option 5.1
Coordinate correction of non-compliant information containers
- Sends 5: Non-conformance notice and required model revisions to Lead appointed party (reject)
Project Coordinator
A function the scenario names
No part in this stage.
Lead appointed party
ISO 19650 party
- Receives 5: Non-conformance notice and required model revisions from Information Manager (BIM) (reject)
Contractor
ISO 19650 party
No part in this stage.
No part in this stage: Project Coordinator, Contractor.
Hand-offs at this stage
5Non-conformance notice and required model revisions
- From
- Information Manager (BIM)
- To
- Lead appointed party
- Hand-off
- Reject, returns to stage 5: Assure federated models and asset data
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 5 | Information Manager (BIM) | Lead appointed party | RejectReturns to stage 5: Assure federated models and asset data | Non-conformance notice and required model revisions |
Checklist
0 of 7 ticked- Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the evidence: Review the information model against defined acceptance criteria - Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Exchange Information Requirements (EIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Exchange Information Requirements (EIR)
- Review the information model against defined acceptance criteria · Action Statement · Verified
- Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the evidence: Review the information model against defined acceptance criteria - Master Information Delivery Plan (MIDP) · Information Use · Verified
The lead appointed party shall establish a detailed responsibility matrix, to confirm the information to be produced, when the information is to be exchanged with whom, and which task team is responsible for its production. In doing this, the lead appointed party shall consider: – the information delivery milestones; – the capability and capacity across the delivery team; © ISO 2020 – All rights reserved 15 --- ISO/FDIS 19650-3:2020(E) - the asset information production methods and procedures; -5.3.1 Nominate individuals to undertake the information management function › 5.4 Information management process – Appointment › 5.4.2 Establish the delivery team's detailed responsibility matrix
See the evidence: Master Information Delivery Plan (MIDP)
- Review the information model against defined acceptance criteria · Action Statement · Verified
- Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the evidence: Review the information model against defined acceptance criteria - Common Data Environment (CDE) solution and workflow · Information Use · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Common Data Environment (CDE) solution and workflow - Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes
- Review the information model against defined acceptance criteria · Action Statement · Verified
- Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the evidence: Review the information model against defined acceptance criteria - Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Exchange Information Requirements (EIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Exchange Information Requirements (EIR)
- Review the information model against defined acceptance criteria · Action Statement · Verified
- Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the evidence: Review the information model against defined acceptance criteria - Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Exchange Information Requirements (EIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Exchange Information Requirements (EIR)
- Review the information model against defined acceptance criteria · Action Statement · Verified
- Project information standard · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information standard - Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the evidence: Review the information model against defined acceptance criteria
- Project information standard · Information Use · Verified
- Common Data Environment (CDE) solution and workflow · Information Use · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Common Data Environment (CDE) solution and workflow - Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes
- Common Data Environment (CDE) solution and workflow · Information Use · Verified
Stage 6: Transfer verified AIM to post-primary school operations
Information Manager (BIM)
Facilitate transfer of verified Asset Information Model containers into ETB operational systems and document information management lessons learned.
Responsible: Information Manager (BIM)
Who does what at this stage
Information Manager (BIM)
The role
Carries out stage 6
Transfer verified AIM to post-primary school operations
- Sends 6: Verified Asset Information Model and assurance sign-off to Project Coordinator (issue)
Project Coordinator
A function the scenario names
- Receives 6: Verified Asset Information Model and assurance sign-off from Information Manager (BIM) (issue)
Lead appointed party
ISO 19650 party
No part in this stage.
Contractor
ISO 19650 party
No part in this stage.
No part in this stage: Lead appointed party, Contractor.
Hand-offs at this stage
6Verified Asset Information Model and assurance sign-off
- From
- Information Manager (BIM)
- To
- Project Coordinator
- Hand-off
- Issue
| No. | From | To | Hand-off | Item |
|---|---|---|---|---|
| 6 | Information Manager (BIM) | Project Coordinator | Issue | Verified Asset Information Model and assurance sign-off |
Checklist
0 of 6 ticked- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Asset Information Requirements (AIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Asset Information Requirements (AIR) - Asset Information Model (AIM) · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Asset Information Model (AIM) - Federated Information Model · Information Use · Verified
Information management is distinct from information production and delivery, but is closely linked to them. Information management should be applied during the whole life cycle of the asset. Information management functions should be assigned to the most appropriate organizations (appointing party, appointed parties, lead appointed parties) and should not necessarily require appointment of new organizations. The quantity of information being managed generally increases both during the delivery p6.3.1 General principles › 13 Summary of “building information modelling (BIM) according to the ISO 19650 series”
See the evidence: Federated Information Model
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Coordinate the transfer of project information containers from the Project Information Model (PIM) to the Asset Information Model (AIM) · Action Statement · Suggested – reviewSee the evidence: Coordinate the transfer of project information containers from the Project Information Model (PIM) to the Asset Information Model (AIM)
- Asset Information Model (AIM) · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Asset Information Model (AIM)
- Coordinate the transfer of project information containers from the Project Information Model (PIM) to the Asset Information Model (AIM) · Action Statement · Suggested – reviewSee the evidence: Coordinate the transfer of project information containers from the Project Information Model (PIM) to the Asset Information Model (AIM)
- Common Data Environment (CDE) solution and workflow · Information Use · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Common Data Environment (CDE) solution and workflow - Asset Information Model (AIM) · Information Use · Verified
1.1 appoint individuals to undertake the information management function 1.2 establish organizational information requirements 1.3 identify assets for which information shall be managed 1.4 identify the asset information requirements 1.5 identify the foreseeable trigger events for which information shall be managed 1.6 establish the asset information standard 1.7 establish the asset information production methods and procedures 1.8 establish the reference information and shared resources 1.9 estKey
See the evidence: Asset Information Model (AIM) - Federated Information Model · Information Use · Verified
Information management is distinct from information production and delivery, but is closely linked to them. Information management should be applied during the whole life cycle of the asset. Information management functions should be assigned to the most appropriate organizations (appointing party, appointed parties, lead appointed parties) and should not necessarily require appointment of new organizations. The quantity of information being managed generally increases both during the delivery p6.3.1 General principles › 13 Summary of “building information modelling (BIM) according to the ISO 19650 series”
See the evidence: Federated Information Model
- Common Data Environment (CDE) solution and workflow · Information Use · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Common Data Environment (CDE) solution and workflow - Exchange Information Requirements (EIR) · Information Use · Verified
The appointing party establishes exchange information requirements (EIR) for each lead appointed party appointment, considering, where appropriate, the organizational information requirements (OIR), asset information requirements (AIR) and project's information requirements (PIR) (see EN ISO 19650-1:2018, 5.1, Figure 2 and explanations in EN ISO 19650-1:2018, 5.2 to 5.7). The requirements for the EIR are specified in EN ISO 19650-2:2018, 5.2.1. An EIR is made available for all prospective lead a4 General › 4.2 Invitation to tender
See the evidence: Exchange Information Requirements (EIR) - Coordinate the transfer of project information containers from the Project Information Model (PIM) to the Asset Information Model (AIM) · Action Statement · Suggested – reviewSee the evidence: Coordinate the transfer of project information containers from the Project Information Model (PIM) to the Asset Information Model (AIM)
- Common Data Environment (CDE) solution and workflow · Information Use · Verified
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Common Data Environment (CDE) solution and workflow · Information Use · Verified
OGP BIM mandate set out to require organisations to meet the standards of the ISO 19650 series, and these standards are used on an international basis. The ISO 19650 series were identified to be adopted into the CWMF on a phased basis to impose the standard on information management for project delivery across the public sector. A key step identified in BIM and the CWMF is to create a structured BIM Implementation Plan (BIP) to detail everyone’s roles and define the goals and requirements using Production › 2.5 Project Specific Initiatives › 3.5 Use of Standards and Protocols
See the evidence: Common Data Environment (CDE) solution and workflow - Project information standard · Information Use · Verified
| Applicable Industry standards | Titles | Version | Clause/Sections | | I.S. ISO 19650-1 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management using building information modelling: Concepts and principles | 2018 | | | I.S. ISO 19650-2 | Organization and digitization of information about buildings and civil engineering works, including building information modelling -- Information management Instruction › Supporting Information
See the evidence: Project information standard
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
- Capturing the Appointing Party's key decision points and Project Information Requirements (PIR), Organisational Information Requirements and Asset Information Requirements (AIR) - Documenting and validating the Information requirements within the Appointing Party Exchange Information Requirements (EIR) - Responsible for appointing individuals to undertake the information management function - Ensuring availability of the Common Data Environment (CDE) (when hosted by the Appointing Party) - Ens9. IM Dimensions: 4D, 5D, Carbon and H&S › B.1 Information Management Roles and Responsibilities › B.1.1 Employer/Client Information Manager (Appointing Party)
See the evidence: Provide assurance regarding adherence to information management processes - Information management function schedule and resourcing records · Information Use · Verified
The information management function response informs the appointing party who (named individual) will be responsible for information management during the project. This will include the lead appointed party and known task team's information manager at pre-appointment. At appointment all task team's information manager should be included. The response shall demonstrate that the proposed individual is competent to perform the function. This also gives the delivery team clarity about the allocation6.2 Information management function
See the evidence: Information management function schedule and resourcing records
- Provide assurance regarding adherence to information management processes · Action Statement · Verified
Evidence for the flow
- E1
Review the information model against defined acceptance criteria · Action Statement · Verified
The appointing party shall undertake a review of the information model in accordance with the project's information production methods and procedures. In doing this, the appointing party shall consider: - the deliverables listed in the master information delivery plan; - the appointing party's exchange information requirements; - the acceptance criteria for each information requirement; and - the level of information need for each information requirement. If the review is successful, the appoint5.7 Information management process – Information model delivery › 5.7.4 Review and accept the information model
See the full evidence entry
Need this flow in your own tooling? Take an editable copy. It is a one way extract, so edits will not sync back to this report.
Download editable diagramKey actions
Open an Action Statement in the Record using its link icon. Each opens in a new tab.
1 headline and 10 detailed Action Statements are recorded. 6 key detailed actions are shown here, with accepted actions first. Read all Action Statements in the Full Scenario Record (opens in a new tab)
What this role works with
Information Uses recorded for this scenario. Review their suitability for the intended organisation and project.
- 1Common Data Environment (CDE) solution and workflow
- 2Information management function schedule and resourcing records
- 3Project information standard
- 4Project Information Requirements (PIR)
- 5Exchange Information Requirements (EIR)
- 6Organisational Information Requirements (OIR)
- 7Asset Information Requirements (AIR)
- 8Master Information Delivery Plan (MIDP)
- 9Project information protocol
- 10Information production methods and procedures
- 11Asset Information Model (AIM)
- 12Federated Information Model
How the scenario unfolds
6 stages · 1 decision with 2 optionsOpen a stage to see its activities and decisions. Guidance links open the matching section of the Record in a new tab.
Review existing consultant-managed CDE arrangements and documentation across ETB departments to establish baseline information practices under the CWMF BIM Mandate.
Proposed responsibility: Information Manager (BIM)
Read practical guidance for Audit baseline ETB information management maturity (opens in a new tab)
Define standard Organisational and Asset Information Requirements alongside Project Information Requirements for the €14m post-primary school refurbishment.
Proposed responsibility: Information Manager (BIM)
Read practical guidance for Establish ETB OIR, AIR, and PIR framework (opens in a new tab)
Incorporate the Exchange Information Requirements and project information protocol into CWMF procurement documents, enforcing the Irish BIM Mandate milestones for design and works contracts over €5m and €10m.
Proposed responsibility: Information Manager (BIM)
Read practical guidance for Embed CWMF EIR into appointment documents (opens in a new tab)
Establish the client Common Data Environment workflow with role-based permissions and evaluate the Lead appointed party BIM Execution Plan and Master Information Delivery Plan.
Proposed responsibility: Information Manager (BIM)
Read practical guidance for Configure client CDE and assess lead BEP (opens in a new tab)
Audit federated design models and contractor asset information against defined acceptance criteria, classification standards, and naming conventions.
Proposed responsibility: Information Manager (BIM)
Do the delivered federated models and asset datasets meet EIR acceptance criteria?
Deliverables meet all EIR acceptance criteria. Rejoin at Transfer verified AIM to post-primary school operations in the Record (opens in a new tab).
Information deliverables require corrective revisions.
- Coordinate correction of non-compliant information containers. Issue corrective notices detailing metadata and geometric defects to the delivery team and verify resubmitted containers against the EIR.
Rejoin at Transfer verified AIM to post-primary school operations in the Record (opens in a new tab).
Read practical guidance for Assure federated models and asset data (opens in a new tab)
Facilitate transfer of verified Asset Information Model containers into ETB operational systems and document information management lessons learned.
Proposed responsibility: Information Manager (BIM)
Does the mandate apply?
Ireland – CWMF / Public Works. Applies
As the appointing party (client), you carry the CWMF BIM requirements into the appointments your organisation's public works projects make, from each milestone's date. In force at 28/10/2026: design team (lead appointed / appointed parties), over €5m from 01/07/2026; contractors & supply chain, over €10m from 01/01/2026. Every appointment is covered: design team (lead appointed / appointed parties) from 01/07/2027; contractors & supply chain from 01/01/2028.
Source: CWMF – Public Sector BIM Adoption Timeline. https://cwmf.gov.ie/en/resources/bim/public-sector-bim-adoption-timeline/
Build Digital materials
The material selection and source metadata recorded for this issue. Proposed uses explain how each material supports the workflow; source availability may change.
Supporting materials
This project information standard provides spreadsheet templates and guidance for naming project information in accordance with the Irish National Annex to ISO 19650-2. The support includes the core file-naming workbook, a hyperlink checker, a presentation and a demonstration.
Standard · XLSX
Enforce standardised file naming across all project participants in alignment with the Irish National Annex.
Directly supports establishing the project information standard and verifying submitted container naming compliance.
Included resources
- Project Information Standard – File Naming · primary · XLSX
BD-MAT-3093 · Source revision f3c82554ee73f2db7a730a64ee511aa2d002510d36418243848f00bee156214a
Form for assessing the applicability of Irish BIM mandate requirements to a project.
Tool · XLSX
Verify the mandatory BIM requirements applicable to the school extension project based on capital threshold.
Assists the Information Manager in confirming which phase of the CWMF Public Sector BIM Adoption Timeline applies to the €14m project and what milestones apply.
BD-MAT-3125 · Source revision 7cae75b1e5db6ccc654b62456a86657615f9e6d8cf4b003876e6cfb8a6452ef9
This organisational information-management plan provides client templates for use before starting the delivery of an asset. It supports the Employer, Client or Sanctioning Authority in preparing information-management requirements in line with ISO 19650.
Plan · XLSX
Structure organisational information management governance and templates before embarking on asset procurement.
Provides the appointing party with standard templates to formulate OIR and AIR in compliance with ISO 19650.
Included resources
- Information Management Plan – Organisational · primary · XLSX
BD-MAT-3129 · Source revision 01c52fd94e81455625148fe780f9f9dede429e7d98fbffb63ecd0a8cec847ead
This support presents the CWMF-to-ISO 19650-2 process workflows, including the Stage (i) feasibility study and preliminary report workflow. It is published as a single PDF support for information-management activities across appointing and appointed parties.
Workflow · PDF
Map traditional CWMF project stages to ISO 19650-2 delivery activities and appointing party decision points.
Crucial for aligning Irish public sector capital stages with exchange information requirements and gateway sign-offs.
Included resources
- Process Workflows CWMF to ISO 19650-2 · primary · PDF
BD-MAT-3134 · Source revision 099ea73d72c1bff960041a4c46f4926277c1ebf1c4af142aefa52b661fedde73
Editable appointing-party workbook covering requirements, responsibilities, mobilisation and delivery planning.
Plan · XLSX
Author comprehensive appointing party requirements and information protocols for inclusion in the appointment documents.
Furnishes editable workbooks required to assemble project-level EIR and information standards for procurement.
BD-MAT-3137 · Source revision bf6f773aa1546f8dc146352cf986ba3190fe68c329532322a54e51f1466c5385
Information management requirements for the operational phase of assets.
Guide · PDF
Guide operational phase information requirements and handover procedures under ISO 19650-3.
Informs the formulation of asset requirements and the protocol for transitioning data containers from PIM to AIM.
BD-MAT-3272 · Source revision def8de4193f95c21a2b0fc29eaeba6637697291e7bd756eaf3315bbc59baa4ec
This report defines Information Manager (BIM) role profiles for the Irish built-environment sector. It supports the development of the digital capability needed for more transparent, consistent and long-term infrastructure delivery.
Report · PDF
Define clear responsibilities and capabilities for client information management personnel and appointed parties.
Guides the client in appointing individuals to the information management function and allocating tasks.
Included resources
- Information Manager (BIM) Role Profiles · primary · PDF
BD-MAT-3714 · Source revision 70de02c1fbe66594f4c0ef99a9ce4575d4aa8784220ef8cfda9680c0d25725c6
Guidance for applying Uniclass within Irish BIM mandate and project-delivery requirements.
Guide · PDF
Standardise classification tables across design elements and operational school assets under Irish public works.
Ensures that asset tagging in the EIR and model checks adheres to the classification tables (for example Uniclass) adopted in the ETB's information standard.
BD-MAT-3875 · Source revision 71f4db228cc803bf2d1fc1fda445fdffb1ae14abe2efe8cff1e072145352236b
This technology evaluation method provides a structured and transparent approach for assessing digital tools that support Information Management and Building Information Modelling (BIM). It establishes consistent criteria for evaluating functionality, interoperability, usability, compliance with standards such as ISO 19650, and alignment with organisational needs. The method supports objective comparison, informed decision-making, and proportionate investment, ensuring that technology acts as an enabler of defined processes rather than a driver in itself. Overall, it helps organisations select and implement technology solutions that are fit for purpose, scalable, and supportive of long-term Information Management / BIM adoption and continuous improvement.
Protocol · XLSX
Provide structured criteria for selecting and testing Common Data Environment platforms against ISO 19650 standards.
Assists the client in evaluating CDE functionality, security permissions, and workflow capabilities.
Included resources
- BIM Technology Evaluation Methodology · primary · XLSX
BD-MAT-3881 · Source revision 3e4ee37a5210f4ea5dcb4a103473d99828b14ea1b12ac4c21a1f56bc244ff410